In a multi-master replication (MMR) deployment, two Directory Server instances are installed on different hosts. It is possible to run the hosts on different operating systems, but in this scenario, both hosts are running on the same operating system.
Table 10–1 and Figure 10–2 illustrate how the Identity Synchronization for Windows components are distributed between the two hosts.
Table 10–1 Component Distribution in a Multi-Master Replication Deployment
The migration process keeps on-demand password synchronization running continuously on the preferred master or on the secondary master.
If both hosts are running on a Solaris operating system, then a third host running Windows 2000 with Active Directory is required for synchronization purposes only. (No components would be installed on the third host.)
The following figure illustrates the process for migrating Identity Synchronization for Windows in a MMR deployment.