Example—Daily Incremental, Weekly Cumulative Backups

The following table shows a schedule where each weekday tape contains only the files that changed since the previous day. In addition, each Friday's tape contains all files changed since the initial level 0 backup at the beginning of the month.

Table 46–11 Daily Incremental, Weekly Cumulative Backup Schedule
 

Floating 

Mon 

Tues 

Wed 

Thurs 

Fri 

1st of Month 

 

 

 

 

 

Week 1  

 

Week 2  

 

Week 3  

 

Week 4 

 

The following table shows how the contents of the tapes can change across two weeks with the daily incremental, weekly cumulative schedule. Each letter represents a different file.

Table 46–12 Contents of Tapes for Daily Incremental, Weekly Cumulative Backup Schedule
 

Mon 

Tues 

Wed 

Thurs 

Fri 

Week 1  

a b 

c d 

e f g 

hi 

a b c d e f g h i 

Week 2 

 

j k l 

n o 

p q 

a b c d e f g h i j k l m n o p q r s 

Tape Requirements for Daily Incremental, Weekly Cumulative Schedule

With this schedule, you need at least 9 tapes if you want to reuse daily tapes, which is not recommended. Preferably, you need 21 tapes if you save weekly tapes for a month: one tape for the level 0, four tapes for the Fridays, and four or 16 daily tapes.

If you need to restore the complete file system, you need the following tapes: