Analyzing Manufacturing

This chapter provides an overview of production analysis, lists a prerequisite, and discusses how to:

Click to jump to parent topicUnderstanding Production Analysis

PeopleSoft Cost Management enables you to manage and evaluate cost performance. When you are in the process of manufacturing items, you can generate inquiries and reports that depict potential production variances and that notifies the appropriate individuals of the variances through workflow. After you close production to accounting, you can run detailed reports that analyze production variances and WIP inventory value.

Click to jump to parent topicPrerequisite

Before using this chapter, review the closing production and reopening production sections of the PeopleSoft Manufacturing PeopleBook.

See Also

Closing Production

Click to jump to parent topicAnalyzing Production Variances for Standard Cost Items

When you close a production ID or production quantity for accounting, PeopleSoft Manufacturing calculates variances. The variances capture the differences between the cost of what is built and the frozen standard cost of the item. The process breaks down the variances by reason, such as: configuration, usage, component yield, lot size, routing process, rework, teardown, outside processing, and output mix. These variances are summarized up to the production ID and cost element level and are used for accounting and analysis purposes.

Once closed for accounting, PeopleSoft Manufacturing calculates these production variances:

Variance Type

Accounts For

Calculation

Configuration

Difference between the cost of the production ID or production quantity's bill of material (BOM) and the cost of the bill that is used to determine the current production costs.

The system combines material lot size and configuration variances for production schedules. Floor stock and expensed items are not considered part of the configuration.

Quantity differences due to rounding to the appropriate unit of measure are included here.

Summarized for all components, calculated by cost element: [(ISSUE_QTY + YIELD_QTY) * component's this level and lower level costs] - component usage variance - component yield variance - (production ID completion qty * prodcost LL cost) - component total production scrap cost - mix variances- operation yield.

Usage

Cost that is associated with the difference between the component's current scheduled quantity and the actual issue quantity. The current scheduled quantity is based on the number of components that should have been used for the completed assemblies. The actual issue quantity is the number of good components that are consumed for the completed assemblies or kitted to the production ID. Usage variance is not calculated for floor stock or expensed items.

[ISSUE_QTY - (CURR_SCHED_QTY * YIELD/100)] * each element of the component's costs summarized by this level and lower level. The component's current scheduled quantity is adjusted to take into account assemblies that are scrapped before where the component is required. Additionally, the current scheduled quantity is adjusted again when the full production quantity is not completed but production is closed.

Operation yield

Difference between actual scrap and expected scrap at the operation when there is operation yield on the operation list. The difference in scrap quantity is costed at the cumulative cost for the operation at which it is incurred.

Calculated by cost element: {(actual scrap – [operation start quantity * (1– (operation yield/100))]} * cumulative operation cost

Component yield

Cost associated with the difference between the expected and the actual component yield loss of a component in production. Component yield variance is not calculated for floor stock or expensed items.

[(YIELD_QTY - (Current Schedule Qty * 1 - YIELD/100)] * component cost by cost element summarized by this level and lower level. The component's current scheduled quantity is adjusted to take into account assemblies that are scrapped before the component is required. Additionally, the current scheduled quantity is adjusted again when the full production quantity is not completed but production is closed. In this manner, the current schedule quantity is based on the quantity completed multiplied by the quantity per for the component.

Lot size

Difference in per-unit setup, fixed run, and postproduction conversion costs when the system completes assemblies (with a quantity that differs from the average order quantity [AOQ]) at an operation. A material lot size variance accounts for the difference between the production quantity and the AOQ for those components whose production quantity is per order. Lot size variances could occur if you have split a production ID and the parent and child production ID quantity are each less than the assembly item's AOQ.

The system combines material lot size and configuration variances for production schedules.

For labor and machine lot size variance: Calculated by operation: (AOQ - assembly quantity issued to the operation) * (setup, fixed run, or postproduction operation time expressed in hours * corresponding labor or machine rate/AOQ).

For material lot size variance: (AOQ - assembly quantity issued to the operation) * component's this-level plus lower-level costs.

Routing process

Financial impact of changes in an item's routing for a production ID or production run. This includes adding, deleting, or skipping operations and changing work centers or tasks.

Summarized by cost element: Earned labor, machine, and overhead costs from SF_EARNCONCOST - lot size variance - this-level-only assembly scrap - this-level-only assembly completions.

Rework

Total charges that are incurred for the rework production ID are compared to the standard cost of the reworked assembly. The difference is the rework expense.

Standard cost of the reworked assembly - total charges that are incurred for the rework.

Teardown

Total charges that are incurred for the teardown production ID are compared to the standard cost of the assembly that is to be torn down. The difference is the teardown expense. This always includes the This Level Labor costs of the assembly that is torn down as well as any components that are lost in the teardown process. It could also include additional labor and overhead costs if a teardown operation list is used.

(Standard cost of the assembly to tear down + standard cost of any additional components + any labor and overhead added) - (standard cost of component outputs or assembly scrap)

Outside Processing Variance

The difference between the standard outside processing costs of the operation and the vendor's price as stated on the purchase order that is used to manage the subcontracted operation.

(PRICE_PO from the production ID's purchase order - outside processing cost from the production ID's operation list) * quantity that is completed at the subcontract operation.

Mix

The difference between the actual outputs and the expected outputs.

Calculated and totaled by cost element. Applied to all outputs (co-product, by product, waste, and recycle). OUTPUT_LIST.SCHED QTY - OUTPUT_LIST.COMP QTY) * (prodcost TL cost + prodcost LL cost)

Lot Size

The difference between the operations start quantity to the operation's AOQ on which the per unit setup costs are based.

Calculated when production is completed.

Fixed Scrap Lot Size

The difference between the planned and actual setup completion quantity (run start quantity) valued at the fixed scrap cost of the operation.

Calculated when production is completed.

Unit Cost

The difference between a standard cost end item and the rolled up cost that includes any actual cost components.

Calculated when production is completed.

Note. Variances can be incurred depending on the item's unit of measure rounding and precision. If you have a unit of measure for an item that has a precision of 0 to the right of the decimal, the item can be issued only in whole units. If the item is a component on a BOM and has a component yield factor, the system schedules the component on a production ID or schedules only in whole units. However, the cost of the assembly item using the component is calculated by using the fractional quantity. This could result in small variances, because the sum of the scheduled component costs is greater than the cost of the total completed number of assemblies using the component.

Click to jump to top of pageClick to jump to parent topicGenerating Production Variance Reports for Standard Cost Items

PeopleSoft Cost Management provides two reports for analyzing variances:

Potential Production Variance Report

Lists potential variances that exist in production before closing the production IDs and schedules for accounting. You can generate the report when you are in a production status that is in process, pending complete, complete, or closed for labor. Review this report periodically so that you can act to correct potential production problems. In addition, the system can send the report to the appropriate individuals through workflow to notify them of the potential variances. When this report is run, no accounting close occurs, and no variances are posted. This process only calculates and reports the variances based on the current snapshot of production.

Production Variance Report

Lists production variances that exist after you close production IDs and schedules for accounting. Reports all PeopleSoft Manufacturing variances except efficiency and utilization.

See Also

PeopleSoft Cost Management Reports

Analyzing Efficiency Variances and Work Center Utilization

Click to jump to parent topicAnalyzing WIP Inventory Value in Standard Cost Environments

Periodically, you must determine the value of material in process. Use this data to verify the general ledger balance for WIP inventory as well as to provide management with an indication of in-process inventory levels.

In-process inventory includes three parts:

PeopleSoft Manufacturing uses information that is associated with a specific production ID or production quantity as the basis for determining the WIP value; it also maintains a status for all production. WIP value comprises production with a status of:

Production with a status of entered, firmed, released, canceled, or closed for accounting status is not included in the WIP value.

PeopleSoft Manufacturing uses various records to determine WIP value:

Record

Function

Production ID Component List

Determines the components that are used. Maintains the quantity of each component that is issued into production. By costing the component's issued quantity, the system can determine the lower-level costs of the assembly. The component list also contains the rework or teardown assembly issue quantities. This value is determined by multiplying the assembly item's this-level and lower-level costs by the issued quantity.

Earned Conversion Costs

Maintains the labor, machine, and overhead costs that are incurred to date for the production ID or production quantity. This includes conversion costs that are incurred for a subcontracted operation.

Assembly Scrap Costs

Maintains the value of scrapped assemblies to subtract from the in-process value. This includes scrap costs that are incurred for a subcontracted operation.

Production Header Output Record

Contains the quantity that is completed. For a single output production ID or schedule, this is the assembly quantity. For multiple output production, this includes the quantity of primary, co-, and by-product completions. The system also subtracts costed completions from the WIP value.

Click to jump to top of pageClick to jump to parent topicDetermining WIP Value

Use the WIP Inventory Value report to analyze work in process. The basic procedure for determining WIP value is:

The result is inventory remaining in process.

Understanding WIP Inventory Value Report Categories

The categories of cost across the top of the report correspond to the categories that are associated with the cost elements. They are:

PeopleSoft Manufacturing further defines each of these categories:

Summarization Category

Definition

PeopleSoft Manufacturing:

Component costs

These lower-level costs are the costs that are associated with the components that are issued to production.

If the PID is for rework or teardown, these costs represent the assembly items this-level and lower-level costs.

For each component, multiplies the issued quantity by the component's standard cost as its defined in the Current Costs by Item record. It then combines this-level and lower-level costs for a given cost element.

Earned this level costs

The assembly's labor, machine, subcontract, and overhead costs earned to date based on the assembly operation completions that are recorded. Maintained in the SF_EARNCONCOST record.

Subtracts negative records that are associated with a production ID (due to completion reversals or revaluations) from the total.

Waste by-product costs

Costs that are associated with the disposal or removal of waste by-products.

Adds costs due to waste by-products to the total for the cost category. It is determined by multiplying the completed quantity as stated in the Production Output record by the cost of the waste item.

Less assembly scrap

Maintained in the SF_SCRAPCOST record.

Adds negative records (due to reversals of scrap or revaluations) from the total for the cost category.

Less assembly completions

Costs that are associated with the assemblies that are completed to stock.

Determines this value by multiplying the quantity of assemblies that are completed to stock or another production area by the assembly's standard cost. Includes primary item, co-products, and recycle by-products. It combines this-level and lower-level costs for a cost element.

See Also

Defining the Cost Foundation for Makeable Items

PeopleSoft Cost Management Reports

Click to jump to parent topicAnalyzing Efficiency Variances and Work Center Utilization

If you record actual labor and machine hours, you want to analyze efficiency variances and work center utilization. The Efficiency/Utilization report details variances and utilization by work center. Within work centers, the production ID or schedule that utilized the work center is specified.

Efficiency variance is the difference between the actual hours that are expended for an operation and the earned hours for the operation. Earned hours are based on the standard costing labor and machine setup, run, fixed-run, and postproduction times that are specified in the production operation list and on the quantity that is completed at the operation. The system reports efficiency variances for both labor and machine.

Utilization compares the available hours for a work center to the actual hours that are recorded for a work center. Available hours are equal to the scheduled hours (if entered for the work center) during actual labor and machine time recording. If scheduled hours are not entered, available hours are derived from the work center, production, or five-day workweek calendar. The system reports utilization measurements for both labor and machines by work center.

Note. PeopleSoft Manufacturing reports on (but does not post) efficiency variances and utilization calculations.

Click to jump to parent topicDisplaying Scrap and Standard Earned Conversion Costs

Periodically, you want to monitor scrap and earned conversion costs that are associated with production. Viewing this information enables you to see how the manufacturing floor is performing. PeopleSoft provides you with the ability to view scrap and earned conversion costs against production IDs and production schedules in the production environment.

Earned conversion costs are calculated for:

Labor or Machine Setup

Setup time converted to hours multiplied by the labor or machine setup rate. Setup is earned when the first completion is recorded for the operation or when the SetUp Complete check box is selected during the recording of completions and scrap for an assembly.

Labor or Machine Fixed Run

Fixed run time converted to hours multiplied by the labor or machine fixed run rate. Fixed run is earned when the first completion is recorded for the operation.

Labor or Machine Run

When the run labor or machine rate is in terms of a rate per hour, the run times (or run rates) are converted to an amount per hour multiplied by the quantity completed, which is then multiplied by the labor or machine rate. When the labor or machine rate is in terms of an amount per unit, the per-unit amount is multiplied by the quantity that is completed.

Labor or Mach Post Production

Post production time converted to hours, multiplied by the labor or machine post production rate. Post production time is earned when the Post Production check box is selected during the recording of completions and scrap for an assembly or when a production ID or schedule is closed for accounting.

Click to jump to top of pageClick to jump to parent topicPages Used to Display Scrap and Earned Conversion Costs

Page Name

Definition Name

Navigation

Usage

Scrap List by Operation

SF_SCRAP_INQ_OP

Production Control, Close and Analyze Production, Review Scrap Cost, Scrap List by Operation

After entering data in the Production Selection page, you can view scrap information by operation sequence for a specific production ID or production schedule.

Scrap Cost Detail

SF_SCRAP_INQ

Production Control, Close and Analyze Production, Review Scrap Cost, Scrap Cost Detail

After entering data in the Production Selection page, you can view detailed scrap costs for the production ID or schedule broken down by operation sequence.

Earned Conversion Cost by Operation

SF_EARNCON_INQ_OP

Production Control, Close and Analyze Production, Review Earned Conversion Costs, Earned Cost by Operation

After entering data in the Production Selection page, you can view conversion cost information by operation sequence for a specific production ID or production schedule.

Earned Conversion Cost Detail

SF_EARNCON_INQ

Production Control, Close and Analyze Production, Review Earned Conversion Costs, Earned Cost Detail

After entering data in the Production Selection page, you can view earned conversion cost detail for production.

Click to jump to parent topicDisplaying Actual Labor Information

Use the Actual Labor inquiry pages to display a summary of the actual labor and machine hours, by operation or work center, recorded for a particular date, and to display those same actual hours in more detail by the type of labor or machine that is performed.

Click to jump to top of pageClick to jump to parent topicPages Used to Display Actual Labor Costs

Page Name

Definition Name

Navigation

Usage

Actual Hours by Operation

SF_ACTHRS_INQ_GRD

Production Control, Close and Analyze Production, Review Actual Hours, Actual Hours by Operation

After entering data in the Production Selection page, you can view actual labor and machine hours for a production ID or schedule by operation.

Actual Hours Detail

SF_ACTHRS_INQ

Production Control, Close and Analyze Production, Review Actual Hours

After entering data in the Production Selection page, you can view detailed information on actual labor and machine hours for a production ID or schedule by operation.

Crew/Machine Resources Detail

SF_ACTHRS_INQ_SEC

Click the Show Crew/Machine Resources button on the Actual Hours Detail page.

View the details for the crew or machine.