Subcontracting

This chapter provides an overview of subcontracting using PeopleSoft Manufacturing and discusses how to:

Click to jump to parent topicUnderstanding Subcontracting Using PeopleSoft Manufacturing

In the shop floor environment, you may need to send components or end items to outside vendors for end item processing, rework, inspection, or testing. PeopleSoft Manufacturing enables you to track production progress and outside processing vendor costs associated with subcontracting using production IDs.

Although managing production with subcontracted operations is similar to managing production for in-house production, there are some differences:

Click to jump to top of pageClick to jump to parent topicManage Production with Subcontracted Operations

To manage production with subcontracted operations:

  1. Record completed operations and scrap for in-house production for operation sequences prior to the subcontracted operation.

    See Manage Production Using Discrete Orders.

  2. Use the Record Completions/Scrap component to make data entry corrections if required.

  3. Use the Select Subcontract Production page to generate the file for subcontracted operations to be used by the Create Purchase Orders process (PO_POCREATE).

  4. Generate the purchase order for outside processing, and approve and dispatch the purchase order to the vendor.

    If a subcontracted item is associated with a subcontracted operation, then the purchase order will be generated with the subcontracted item and its purchasing attributes and contract information (if available) during the creation of the purchase order.

    Use the PO Stage Load, PO Calculations, PO Creation, Approve Amounts, Approve ChartFields, and Dispatch POs components in PeopleSoft Purchasing to process the subcontracted purchase order.

  5. Send end items to outside vendors for subcontracted processing.

  6. Receive end items back from vendors using the Receiving page in PeopleSoft Purchasing.

    See Processing Receipts.

  7. Use the Subcontracted Receipt page to record completed subcontracted operations and scrap for the manufactured end item.

  8. (Optional) Edit components.

  9. Record completions and scrap for any additional in-house operations for the manufactured end item.

    See Recording Completions and Scrap Using Electronic Data Collection.

  10. Move completed end items out of production.

  11. Run the Completions Update process (SFPDCDRV).

  12. Use the Complete Production page to indicate that production for all operations has been completed.

  13. (Optional) Record actual labor and machine hours associated with the subcontracted operations.

Click to jump to parent topicPrerequisites

Prior to scheduling a subcontracted operation:

Click to jump to parent topicCommon Elements Used in This Chapter

Production ID

The production order identifier.

Production Area

The production area identifier where the manufacturing process occurs.

Item ID

The name and description of the item being manufactured.

Note. Subcontracted items that are processed (manufactured) by an outside vendor will also be included.

Prdn Type (production type)

The type of production: Production, Rework, or Teardown.

BOM Code

The BOM identifier used during the manufacturing process.

Routing Code

The routing identifier used during the manufacturing process.

Revision

The revision identifier if the item is revision-controlled.

Click to jump to parent topicSelecting Subcontracted Operations for Purchase Order Creation

When part or all of the manufacturing process is done at an outside vendor, you need to generate purchase orders for production IDs with subcontracted operations. Use purchase orders to authorize a vendor to add labor or material or both to a partially completed end item.

Using the Select Subcontract Prdn for PO page in PeopleSoft Manufacturing, you select one or more production IDs, production areas, or item IDs for which to generate purchase orders for subcontracted operations. When you run the Select Subcontract Prdn for PO process (SFS5000), the system automatically transfers the subcontracted operations information for purchase order creation to PeopleSoft Purchasing, including production ID and subcontracted information (vendor name and manufactured item or subcontracted item) for which the outside processing must be done as well as the operation sequence associated with the outside operation. Once the subcontracted purchase order is generated, it is processed like any regular purchase order within PeopleSoft Purchasing.

To create purchase orders for subcontracted operations, verify that:

Completing Operations and Scrap for Production Using Count Points

If you're using count points, then all subcontracted operations must be defined as count point.

Click to jump to top of pageClick to jump to parent topicPages Used to Generate Subcontracted Purchase Orders

Page Name

Definition Name

Navigation

Usage

Select Subcontract Production

RUN_SFS5000

Production Control, Process Production, Subcontract Production, Subcontract Prdn for PO, Select Subcontract Production

Select production that requires purchase orders for subcontracted operations.

Subcontracted Purchase Order Report

RUN_SFS2008

Production Control, Process Production, Subcontract Production, Subcontracted PO Report

View the status of purchase orders that you've requested for subcontracted production.

Subcontract Components Report

RUN_SFS5001

Production Control, Process Production, Subcontract Production, Subcontract Components Report

Displays the production IDs and the components associated with subcontracted operations.

See SFS5001 - Subcontract Components Report.

Click to jump to top of pageClick to jump to parent topicSelecting Production to Generate Purchase Orders

Access the Select Subcontract Production page (Production Control, Process Production, Subcontract Production, Subcontract Prdn for PO, Select Subcontract Production).

Selection Criteria

Select the options indicating the production to generate purchase orders for subcontracted operations. Options are:

  • Start Date

  • Prdn ID (production ID)

  • Prdn Area (production area)

  • Item ID

Run

Click to run this request. Process Scheduler runs the Select Subcontract PO for Prdn process (SFS5000) at user-defined intervals.

Extract to PO only when prior Op Seq is complete

Select this check box to ensure that the subcontract purchase order is created only after the prior operations are complete, thereby eliminating change orders.

Click to jump to top of pageClick to jump to parent topicGenerating, Approving, and Dispatching Purchase Orders for Subcontracted Operations

Once you run the Select Subcontract Prdn for PO process, the purchase orders for the subcontracted services can be generated.

To generate, approve, and dispatch the subcontracted purchase order:

  1. Run the PO Stage Load process (PO_POSTAGE).

    This process is run with the PO Stage Load page (Purchasing, Purchase Orders, Stage/Source Requests). This process takes all the requests generated from requisitions, PeopleSoft Supply Planning, and PeopleSoft Manufacturing, and stages them for the actual purchase order creation.

  2. Run the PO Calculations process (PO_POCALC).

    This process is run with the PO Calculations - Run Controls page (Purchasing, Purchase Orders, Stage/Source Requests).This is an Application Engine process that does most of the processing to create a purchase order.

  3. Run the Create Purchase Orders process (PO_POCREATE).

    This process is run with the Create PO page (Purchasing, Purchase Orders, Stage/Source Requests). This is an Application Engine process that generates the purchase orders that will be staged for approval and dispatching.

    If a recommended vendor was listed on the subcontracted task or operation, the purchase order is created with the vendor specified. If the vendor field was left blank on the routing or operation list for the production ID, the suggested vendor, as defined in PeopleSoft Purchasing, is selected.

    The system-generated purchase order for the subcontracted service contains this data:

  4. Once you've created the purchase orders, you must approve and dispatch them before you can send the purchase order to the vendor.

    Use the Amount Approval, ChartField Approval, and Dispatch POs components to approve and dispatch the purchase orders for the subcontracted operations.

See Also

SFS2008 - Subcontracted Purchase Order Report

Click to jump to parent topicManaging Purchase Order Changes

Sometimes you may need to change a purchase order to respond to production changes. If a purchase order for subcontracting production has been created and a production change requires a change to the purchase order, PeopleSoft Manufacturing sends a purchase order change request to PeopleSoft Purchasing. This request indicates that a purchase order change is required for the subcontracted purchase, and either a purchase order change request is processed or a new purchase order needs to be generated.

You may also need to change the purchase order when any end items have been returned from the vendor as scrap.

If a subcontracted operation has more than one purchase order, the system will not automatically create change requests. You will need to manually create the change requests.

A purchase order change may be necessary when there is a change to:

The purchase order change request is processed by PeopleSoft Purchasing using the Change Load Application Engine process (PO_CHNGLOAD) and the Change Purchase Order Application Engine process (PO_POCHNG).

After you request a purchase order and run the PO Stage load process, the subcontracted operation has an In Process status, after PeopleSoft Purchasing has received and acknowledged the subcontracted operation information.

If you use the background reschedule process to reschedule production with subcontracted operations, and the purchase order date is no longer valid, the system cannot reschedule an In Process purchase order. When running the background reschedule process, you can request that the system check for any production that has an In Process purchase order for subcontracted operations. In this case, the system displays an error message for each instance, unless you decide to skip further in process messages. You can then contact the purchasing department to reschedule the purchase order.

If multiple subcontracted purchase orders exist for the same subcontracted operation, no change order requests will be created from PeopleSoft Manufacturing.

Click to jump to top of pageClick to jump to parent topicCanceling or Deleting a Subcontracted Purchase Order

If you cancel or delete the subcontracted PO, line, or schedule, the system resets the subcontracted purchase order status for the associated production ID or operation sequences associated with the purchase order, line, or schedule. Therefore, you need to rerun the process to generate a subcontracted purchase order.

Click to jump to parent topicReceiving End Items from Vendors

Receiving the end items back from the vendor is a two-step process, but the process can be streamlined so that it is only one step. The process to receive the end items using the two-step process is:

  1. Receiving records the receipt of the end items back from the vendor.

  2. Production records the operations completions and scrap for the received end items.

If you setup subcontract streamlining in PeopleSoft Purchasing, then the process to receive end items is that the Receiving functionality records the receipt of the end items back from the vendor. Upon saving the receipt the system will perform the purchase order receipt and the production ID completion in one step by automatically generating electronic data collection transactions for the subcontracted completions data. To specify that you want to use subcontracting streamlining, select the Interface Receipt and Subcontract Streamline check boxes on the Maintain Receipts - Receiving page.

See Managing Receipts.

Once the vendor has completed the subcontracted work, the end items are returned to Receiving. To receive end items back from the subcontractor, use the Maintain Receipts - Receiving page.

During the receiving process, the end items can be inspected and accepted or rejected from the vendor. Receiving assigns one of these indicators to the rejected quantity when recording the receipt:

Return for Replacement

Return the end item to the vendor with the expectation that it will be replaced. The return quantity is equal to the reject quantity with a reject action of Return to Replacement.

The received rejected quantity for production is the received quantity and the received rejected quantity is zero.

PeopleSoft Purchasing does not record the replacement quantity as either accepted or rejected.

Return for Credit

Return the end items back to the vendor for a credit. The credited amount is the subcontracted service charge.

PeopleSoft Purchasing records the Reject quantity as scrap on the production Subcontracted Receipt page.

This table summarizes the receiving reject actions and effects:

Action

Receiving Record

PS_RECV_SUBREC_MG

Purchase Order Line

Return for Replacement

No reject qty

No scrap

No update

Return for Credit

Scrap the qty

Scrap the qty

Update

Subcontracted receipts to stock are prevented if the end item or a component of the end item is on hold and the order is for regular production. Subcontracted receipts to intermediate operations are allowed for regular production.

The PeopleSoft Purchasing receipt process updates production to indicate that the end items have been received. You cannot record operation completions or scrap until the end items have been received.

In addition, you cannot close production until the quantity of end items sent to the vendor is equal to the quantity of scrapped and completed end items received back from the vendor and recorded complete in production.

PeopleSoft Purchasing can optionally receive end items using electronic data collection. Electronic data collection transactions for manufactured end items automatically record the subcontracted completions data. You do not need to record completions in the Subcontracted Receipt pages for these subcontracted end items. After the transactions are recorded and staged, run the Completions/Scrap Update process to update the production balances.

Click to jump to parent topicRecording Completed Operations and Scrap for Subcontracted Operations

Once you've processed the end items through receiving and inspection, you can record the operation as complete in PeopleSoft Manufacturing. If the subcontracted operation is the last operation on the routing, you can also indicate that production is completed.

When you record scrap for the end item, the system optionally sends a workflow notification to selected roles defined by you. These roles might include a quality manager or a production control manager.

If you are integrating with a Manufacturing Execution System (MES), you can receive subcontracted operation completions from the MES to the PeopleSoft system. The end items need to be received in PeopleSoft Purchasing before you can record the completion transaction in PeopleSoft Manufacturing. The MES sends the same information for a subcontracted completion as with completions for regular operations.

Note. If you have set up your environment to perform subcontract streamlining then the recording of subcontracted operations is unnecessary.

See Also

Integrating PeopleSoft Manufacturing with a Third-Party System

Understanding SCM Integration

Click to jump to top of pageClick to jump to parent topicPages Used to Record Completions and Scrap for Subcontracted Operations

Page Name

Definition Name

Navigation

Usage

Subcontracted Receipt

SF_SUBREC

Production Control, Process Production, Subcontract Production, Receive Subcontract Assembly, Subcontracted Receipt

Record completed operations and scrap by subcontracted operation.

Note. You must receive the subcontracted end items through PeopleSoft Purchasing before using this page.

Complete Production

SF_COMPL_PRDN

Production Control, Process Production, Subcontract Production, Receive Subcontract Assembly, Subcontracted Receipt

Click the Complete Production link.

Indicate that production is completed for production IDs with subcontracted operations.

Receipt Information

SF_RECEIPT_INFO

Production Control, Process Production, Subcontract Production, Receive Subcontract Assembly, Subcontracted Receipt, Receipt Information

View receipt and completions information about the subcontracted operation.

Record Completions/Scrap

SF_COMPL_ID

Production Control, Process Production, Complete Production, Record Completions/Scrap

(Optional) Enter completions and scrap information for production IDs.

In addition, use this page to move end items for production IDs with a single output or multiple outputs.

Production Scrap Details

SF_COMPL_SCRAP

Production Control, Process Production, Complete Production, Record Completions/Scrap

Click the Enter Scrap Data link.

Enter scrap quantities, if applicable.

Apply Defaults

SF_COMPL_DEFAULTS

Production Control, Process Production, Complete Production, Record Completions/Scrap

Click the Apply Defaults link.

Select the default putaway or alternate storage locations for the completed end items.

Rapid Serial Numbers

AUTO_SERIAL_WRK

Production Control, Process Production, Complete Production, Record Completions/Scrap

Click the Generate Serial IDs link.

(Optional) Automatically generate serial numbers for production end items that are serial-controlled.

Note. You must define serial-controlled items in PeopleSoft Inventory.

Lot/Serial Number Selection scroll area

SF_ED_CMP_SBP_GRD

Production Control, Process Production, Complete Production, Record Completions/Scrap, Edit/Issue Express

Click the Select Lot/Serial link.

(Optional) Identify the lots from which you want to consume lot-controlled components.

You must enter a pending quantity greater than zero for a lot-controlled component before the Lot/Serial scroll area is available.

Production History

SF_TRANSHIST

Production Control, Define Production, Review Production Information, Production History

View production transaction history for production IDs.

Production History - Detail inquiry

SF_TXN_HIST_SP

Production Control, Define Production, Review Production Information, Production History

Click the Detail button on the Production History page.

View production transaction history details based on:

  • Completions detail

  • Component consumption

  • Operation detail

Click to jump to top of pageClick to jump to parent topicRecording Completed Subcontracted Operations and Scrapped End Items

Access the Subcontracted Receipt page (Production Control, Process Production, Subcontract Production, Receive Subcontract Assembly, Subcontracted Receipt).

Print at Save

Select this check box if you want to print production documents at save time.

Setup Print Options

Click this link to access the Process/Output Options page to select different print criteria for the production documents.

Completed Qty (completed quantity)

Enter the number of end items being completed.

Quality

Click this link to initiate a data entry session and to access either the Data Entry - Subgroup Method page or the Data Entry - Sample Method page in PeopleSoft Quality, depending on the data entry method that you specified when creating the quality control plan.

Operations Data

View display-only production data such as assembly start quantities, number of assemblies scrapped, expected completed quantities, and yield percentages for each operation sequence.

See Also

Collecting Quality Data

Click to jump to top of pageClick to jump to parent topicReviewing Subcontract Receipt Information

Access the Receipt Information page (Production Control, Process Production, Subcontract Production, Receive Subcontract Assembly, Subcontracted Receipt, Receipt Information).

Recv Rejected Qty (received rejected quantity)

Displays the quantity that Receiving rejected from the vendor and that was recorded in PeopleSoft Purchasing. Receiving assigns one of these indicators to the rejected quantity:

  • Return for Replacement

  • Return for Credit

Only received quantities that have a status of Return for Credit appear in this field.

Prdn Accepted Qty (production accepted quantity)

Displays the quantity that was actually recorded as a completion using the Subcontract Receipt page.

Prdn Rejected Qty (production rejected quantity)

Displays the quantity that was actually recorded as scrap using the Subcontract Receipt page.

Note. Use the Edit Components page if you want to modify or view the components that will be consumed based on the quantity completed or scrapped, or if you need to select the serial or lot numbers for those serial- or lot-controlled components that were consumed when you recorded the completion.

Click to jump to parent topicMoving Completed End Items

The process for moving completed end items for subcontracted operations is the same as for other production.

See Moving Completed End Items and Assigning Serial and Lot Numbers.

Click to jump to top of pageClick to jump to parent topicPages Used to Move Completed End Items

Page Name

Definition Name

Navigation

Usage

Production Selection

SF_COMPL_SELECTION

Production Control, Process Production, Complete Production, Record Completions/Scrap, Production Selection

Select a production ID or production schedule.

Record Completions/Scrap page - Route-To PID/Stor Locations (route to production ID and storage locations) scroll area

SF_COMPL_ID

Production Control, Process Production, Complete Production, Record Completions/Scrap, Production Selection, Record Completions/Scrap

Enter a Completed Qty (completed quantity) and the last Op Seq (operation sequence) to access the Route-To/PID Stor Locations (route to production ID and storage locations) scroll area.

Move completed end items to a production ID or to a storage location.

Shortages

SF_COMPL_SHORTAGE

Production Control, Process Production, Complete Production, Record Completions/Scrap, Production Selection, Record Completions/Scrap

Enter a Completed Qty (completed quantity) and the last Op Seq (operation sequence) to access the Route-To/PID Stor Locations (route to production ID and storage locations) scroll area.

Click the Shortages button in the Route to PID/Storage Locations scroll area.

Select a production ID to which you want to route the completed end item.

Click to jump to parent topicCompleting Production for Subcontracted Operations

The process for completing production for subcontracted operations is similar to the process for other production.

See Running the Completions Update COBOL/SQR Process (SFPDCDRV).

Click to jump to top of pageClick to jump to parent topicPages Used to Complete Production for Subcontracted Operations

Page Name

Definition Name

Navigation

Usage

Production Selection

SF_COMPL_SELECTION

Production Control, Process Production, Complete Production, Record Completions and Scrap, Production Selection

Select a production ID to record completions and scrap.

Record Completions/Scrap

SF_COMPL_ID

Production Control, Process Production, Complete Production, Record Completions and Scrap

Enter completions and scrap information for the production ID.

Complete Production

SF_COMPL_PRDN

Production Control, Process Production, Complete Production, Record Completions and Scrap

Click the Complete Production link.

Indicate that production at all operation sequences has been completed.

Click to jump to parent topicEditing or Issuing Components for Subcontracted Operations

The process for editing or issuing components for subcontracted operations is similar to that of other production.

See Editing Component Lists.

Click to jump to top of pageClick to jump to parent topicPages Used to Edit or Issue Components for Subcontracted Operations

Page Name

Definition Name

Navigation

Usage

Edit/Issue Components Summary

SF_EDIT_COMPS_EDIT

Production Control, Process Production, Subcontract Production, Receive Subcontract Assembly, Edit/Issue Components Summary

Edit or view components.

Edit/Issue Express

SF_EDIT_COMPS_EXPR

Production Control, Process Production, Subcontract Production, Receive Subcontract Assembly, Edit/Issue Express

(Optional) Select lot- or serial-controlled components that have pending issue or pending loss quantities.

Lot/Serial Number Selection

SF_ED_CMP_SBP_GRD

Production Control, Process Production, Subcontract Production, Receive Subcontract Assembly, Edit/Issue Express

Click the Select Lot/Serial link.

(Optional) Select the lot or serial numbers (or both) of the lot- or serial-controlled components to be consumed during the completions process.

You must enter a pending quantity greater than zero for a serial-controlled or lot-controlled component before the Lot/Serial scroll area is available.

Edit/Issue Components Detail

SF_EDIT_COMPS_DET

  • Production Control, Process Production, Subcontract Production, Receive Subcontract Assembly, Edit/Issue Components Detail

  • Production Control, Process Production, Subcontract Production, Receive Subcontract Assembly, Edit/Issue Components Summary

    Click the Detail button next to the component you want to edit or view.

View detailed information for each component for selected production.

Record Completions/Scrap - Production Selection

SF_COMPL_SELECTION

Production Control, Process Production, Complete Production, Record Completions/Scrap, Production Selection

Return components issued during completions or to correct data entry errors. You can also return lot- or serial-controlled end items by using this page.

Record completions for a production ID or a production schedule. To return lot- or serial-controlled end items, first record operations and scrap and put away production with lot- and serial-controlled components.

Record Completions/Scrap

SF_COMPL_ID

Production Control, Process Production, Complete Production, Record Completions/Scrap

Return components issued during completions or to correct data entry errors.

You can also return lot- or serial-controlled end items by using this page.

Production History

SF_TRANSHIST

Production Control, Define Production, Review Production Information, Production History

View production transaction history for components.

Transaction History Details inquiry

SF_TXN_HIST_SP

Production Control, Define Production, Review Production Information, Production History

Click the Detail button.

View completions details based on the selection criteria.

Click to jump to parent topicCreating Reversing Entries

If a data entry error is made when recording end item completions or scrap for a subcontracted operation, input a negative number to reverse the completion or scrap entry. For example, an entry was made to record a completion of eight end items at operation 20, but only six end items were actually completed. Enter a -2 in the Completed Qty field to reverse the original entry of 8. This brings the completed quantity balance for that operation to 6.

This reversing entry:

Creating a Reversing Entry for Subcontracted Operations Using Count Points

If you are performing reversing entries for production IDs with subcontracted operations, you can reverse operations and scrap from one count point (or subcontracted operation) to the prior count point (or subcontracted operation).

See Also

Moving Completed End Items and Assigning Serial and Lot Numbers

Click to jump to top of pageClick to jump to parent topicPages Used to Create Reversing Entries for Subcontracted Operations

Page Name

Definition Name

Navigation

Usage

Production Selection

SF_COMPL_SELECTION

Production Control, Process Production, Complete Production, Record Completions and Scrap, Production Selection

Select a production ID to create reversing entries.

Record Completions/Scrap

SF_COMPL_ID

Production Control, Process Production, Complete Production, Record Completions and Scrap, Production Selection, Record Completions and Scrap

Enter reversing entries for selected production.

Production Scrap Details

SF_COMPL_SCRAP

Production Control, Process Production, Complete Production, Record Completions and Scrap, Production Selection, Record Completions and Scrap

Click the Enter Scrap Data link.

Enter any reversing entries to scrapped quantities, if applicable.

Apply Defaults

SF_COMPL_DEFAULTS

Production Control, Process Production, Complete Production, Record Completions and Scrap, Production Selection, Record Completions and Scrap

Click the Apply Defaults link.

Select the putaway locations for the reversing entries.

Lot/Serial Number Selection

SF_ED_CMP_SBP_GRD

Production Control, Process Production, Complete Production, Record Completions and Scrap, Production Selection, Edit/Issue Express

Click the Select Lot/Serial link.

(Optional) Select the serial numbers of the serial-controlled components to be returned.

Lot/Serial Number Selection scroll area

SF_ED_CMP_SBP_GRD

Production Control, Process Production, Complete Production, Record Completions and Scrap, Production Selection, Edit/Issue Express

Click the Select Lot/Serial link.

(Optional) Identify the lots from which you want to return lot-controlled components.

Click to jump to parent topicRecording and Viewing Actual Labor and Machine Hours

The process for recording actual labor and machine hours for subcontracted production is similar to that of other production.

See Recording Actual Machine and Labor Hours.

Click to jump to top of pageClick to jump to parent topicPages Used to Record and View Actual Labor and Machine Hours

Page Name

Definition Name

Navigation

Usage

Production Selection

SF_ACTHR_SELECTION

Production Control, Process Production, Complete Production, Record Actual Hours, Production Selection

Select the production that you want to record actual machine and labor hours incurred during the production process.

Record Actual Hours

SF_ACTHRS_NEW

Production Control, Process Production, Complete Production, Production Selection, Record Actual Hours

Enter labor and machine hours for the selected production.

Review Actual Hours - Production Selection

SF_ACTHRS_INQUIRY

Production Control, Close and Analyze Production, Review Actual Hours

Select a specific production ID or production schedule to view actual labor and labor information.

Actual Hours by Operation

SF_ACTHRS_INQ_GRD

Production Control, Close and Analyze Production, Review Actual Hours, Actual Hours by Operation

View actual labor and machine hours for a production ID or schedule by operation.

Actual Hours Detail

SF_ACTHRS_INQ

Production Control, Close and Analyze Production, Review Actual Hours, Actual Hours Detail

View detailed information on actual labor and machine hours for a production ID or schedule by operation.

Crew/Machine Resources Detail

SF_ACTHRS_INQ_SEC

Production Control, Close and Analyze Production, Review Actual Hours, Actual Hours Detail

Click the Show Crew/Machine Resources button.

View resource details for the crew or machine.