Battery Service Sequence
In the Sun Datacenter InfiniBand Switch 36 Service Manual for Firmware Version
2.1, the summary of the tasks to service the battery is in the incorrect
sequence. This table corrects the sequence.
|
|
|
1.
|
Determine if the battery is faulty.
|
“Determine If the Battery Is Faulty”.
|
2.
|
Power off both power supplies.
|
“Power Off a Power Supply”.
|
3.
|
Remove all InfiniBand cables.
|
“Remove an InfiniBand Cable”.
|
4.
|
Remove the switch from the rack.
|
“Remove the Switch From the Rack”.
|
5.
|
Replace the battery.
|
“Replace the Battery”.
|
6.
|
Install the switch in the rack.
|
Note -
Do not power on the switch.
|
7.
|
Install all InfiniBand cables.
|
“Install an InfiniBand Cable”.
|
8.
|
Power on both power supplies.
|
“Power On a Power Supply”.
|
|
Note -
You must completely power off the switch before disconnecting the InfiniBand
cables. Similarly, you must attach all InfiniBand cables before powering on the
switch.