Add a formula column
You can add a formula column to the asset sheet. You can create a formula column for data sources that are based on data definitions SYS Numeric Logical Datasource or SYS Date Logical Datasource.
You can define formulas of the following types:
|
•
|
Numeric: Available if the data source is SYS Numeric Logical. It is for creating formulas on numeric field values. |
|
•
|
Data Difference: Available if the data source is SYS Numeric Logical. It is used to create formulas that calculate the difference in days between two dates. |
|
•
|
Date Add: Available if the data source is SYS Date Logical. It can be used to add values to a date to calculate a new date. |
To create a numeric formula
|
1
|
In the Column Properties window, choose Formula and select Numeric. |
|
2
|
Click Create. The Create Formula window for numeric formulas opens. |
|
3
|
Select a data type from the drop-down list. The data types include: |
|
•
|
Asset Item: Data elements that are defined on the asset form along with SYS Numeric Datasource, Sys Business Process Datasource, and Sys Project Cost Datasource data elements. |
|
•
|
Asset Sheet: Columns that are already defined on the asset sheet. |
|
4
|
Build your formula by doing the following: |
|
•
|
To include a data source in the formula, select the data source from the list and click Select. |
|
•
|
Click on mathematical modifiers (plus, minus, etc.) and numbers on the keypad. |
|
5
|
When the formula is complete, click OK. |
To create a date difference formula
|
1
|
In the Column Properties window, choose Formula and choose Data Difference. Click Create. The Date Difference window opens. |
For earlier date and later date, click the Select button. Select a data element. The list includes date type data elements from the asset form or existing date type columns on the asset sheet.
|
2
|
Choose one of the following: |
|
•
|
Calculations based on Calendar Days: Date difference calculation is based on calendar days and does not take company non-working days into account. |
|
•
|
Calculations based on Work Days: Date difference calculation is based on company calendar working and non-working days. |
|
3
|
(Optional) Select Show Partial Days. |
To create a date add formula
|
1
|
In the Column Properties window, choose Formula and choose Date Add. Click Create. The Date Add window opens. |
|
2
|
For the Date field, click Select. Select a data element from the list. The list includes date type data elements from the asset form. |
|
3
|
For the Add field, click Select. Select a data element from the list. The list includes numeric type data elements from the asset form. |
|
4
|
Select one of the following: |
|
•
|
Calculations based on Calendar Days: Calculation is based on calendar days and does not take company non-working days into account. |
|
•
|
Calculations based on Work Days: Calculation is based on company calendar working and non-working days. |