Setting up Multiple Company Calendars

 

Primavera Unifier supports multiple calendars, enabling you to create a library of calendars that can be selected for use at the Company or project/shell levels. The multiple calendars enable you to have calendars to support varying work schedules (depending on locality) and to account for holidays and other non-working days. For example, some countries in the Middle East have weekends that are other than Saturday and Sunday. Unless otherwise specified, the default calendar for a project or shell is the Company calendar that is designated as the default calendar. The calendar selected affects project or shell durations and due dates.

The calendars can be used in project/shell templates, and are automatically applied when the template is updated. Also, users can create activity calendars to use in schedule sheets, specific activities in schedule sheets. Calendars also affect business process task dues dates, workflow due dates, and formula calculations.

Step 1: Set permissions for multiple calendars. Grant permissions to allow the configuration of Company-level multiple calendars. See "Setting Multiple Calendar Permissions".

Step 2: Create and manage calendars (create, copy, modify, delete, set as default). See "Creating Multiple Calendars". and "Modify, delete, or mark a calendar as default".

 

Setting Multiple Calendar Permissions

Creating Multiple Calendars

Modify, delete or mark a calendar as default

 

 

 