Modify step due date

If the step duration and workflow override are enabled on the BP, you can also set the task due date for the next step.

To change the task due date

1 Click the Calendar icon next to the To field. The Task Due Dates window opens.
2 Choose one of the following options:
Set all task due dates as: Lets you set the same due date for all assignees.
Set individual task due dates: Allows you to assign different due dates for each assignee one at a time.
3 Click the Calendar icon corresponding to the option you chose. For the second option, click the Calendar icon next to each user’s name on the list. The Date picker opens.
4 Select the month and year, and then click the date you want to select.

Note: The workflow engine uses the company workday calendar. Grayed-out dates are those that have been set as non-working days (for example, weekends and holidays) by your company administrator. You cannot select non-working days for a task due date.

 

 

 

 