Assign a data source to a project or shell cash flow curve in Cash Flow (Basic)

You can assign a data source to each project or shell cash flow curve. This allows you to plot the project or shell cash flow sheets on program-level and company-level cash flow sheets.

To assign a data source to a cash flow curve

1 In the Cash Flow (Basic) log, select the cash flow curve and click the Properties button.
2 In the General tab, click the Data Source drop-down list and select a data source (Project or Shell Cash Flow 1 through Project or Shell Cash Flow 25). Select a different data source for each curve that you want to track. These will become available to plot in program- and company-level cash flow curves.
3 Click OK.

 

 

 

 