The Options tab is available if the curve type is defined as Calculation in the General tab.
In this field |
Do this |
||||||
Curve Properties |
Select the curve properties. |
||||||
S-Curve |
Specify the S curve properties:
|
||||||
Linear |
Creates a linear curve. |
||||||
Extrapolate based on curve |
Select from the drop-down list of existing cash flow curves. |
||||||
Manual entry intermediate points |
Similar to S-Curve and Linear, this option allows blending of manual and calculation curves by allowing the entry of manual values to a calculation curve. When you choose this option, the cash flow sheet values are calculated, but are also editable. |
||||||
Start Point |
Specify the curve start point. |
||||||
Cost |
Select the curve starting point for cost-based cash flow curves:
|
||||||
Schedule |
Select the starting point for schedule-based cash flow curves:
|
||||||
End Point |
Specify the curve end points. |
||||||
Cost |
Select the curve end point for cost-based cash flow curves:
|
||||||
Schedule |
Select the curve end point for schedule-based cash flow curves:
|
||||||
Source Details |
Click the Details button. The Source Details window opens and displays data based on the chosen information. If the choice for cost and schedule is manual, then it allows you to provide the project or shell cost, and start and end dates. Click OK to save and exit. |
To define project or shell cost and start and end dates for the curve
1 | In the cash flow curve Properties window, click the Details button. The Source Details window opens. |
2 | Define the project or shell cost and start and end dates for the curve. |
• | If the curve is by project or shell, enter the total values by project or shell. |
• | If the curve is by WBS, enter the values for each WBS code. |