You can copy the data from any manual entry column to another.
To add line items by copying existing data from one column to another
1 | Open the project or shell Cost Sheet window, click the Edit menu and choose Copy > Column Data. The Copy Column Data window opens. |
2 | Complete the Copy Column Data window as described in the following table. |
In this field |
Do this |
||||||
Copy type |
Choose one of the following:
|
||||||
Copy from column |
From the drop-down list, select the column to copy. Only line item entry columns will be listed. |
||||||
Percentage |
You may enter a percentage value to copy. For example, if you choose 10%, then 10% of the value of the original column value will be copied into the new column. |
||||||
Copy to column |
From the drop-down list, select the column into which you want the line items copied |
||||||
Rows |
Choose one of the following from which you want to copy the values:
|
3 | Click Copy. The data in the first column will be copied into the second column. |
Oracle Corporation
Primavera Unifier 9.10 • Copyright © 1998, 2012, Oracle and/or its affiliates. All rights reserved.