Distribute and lock the budget

Once the Budget Distribution window has been completed, you can distribute the budget and lock the budget.

To distribute and lock the budget

1 Complete the Budget Distribution window.
2 Click Apply to save changes.
3 Click Save & Lock.
4 When prompted, enter an explanation for locking the budget, then click OK.
5 Click Close to close the Budget Distribution window.

 

 

 

 