Open a generic cost sheet

To open a generic cost sheet

1 Open the shell and click Configurable Manager > Generic Cost Manager > Generic Cost Sheet in the left Navigator. The Generic Cost Sheet log opens.

 

2 Select the cost sheet from the log and click Open. The generic cost sheet opens.

You work with a generic cost sheet in the same way as a standard cost sheet. The difference is that the data in the generic cost sheet comes from shells and subshells rather than from projects. The first two columns are displayed by default. The view is fixed, and there is no split screen capability.

 

 

 

 


Oracle Corporation

Primavera Unifier 9.10 • Copyright © 1998, 2012, Oracle and/or its affiliates. All rights reserved.

Copyright Information