Entering and Viewing Cost Data

In Primavera uDesigner, data elements can be added that allow you to enter and view cost data on schedule sheets. These data elements are Activity Cost 1 (and Activity Total Cost 1 Per WBS) and Activity Cost 2 (and Activity Total Cost 2 Per WBS). The Cost and Per WBS data elements have a predefined association between them. Also, the Activity Latest Progress As Of data element can be added to allow you to track the date of the last change to an activity.

Note: Primavera Unifier refreshes the cost data when you choose File > Refresh in a Schedule Sheet and refresh immediately or set up a refresh frequency. See "Refreshing Schedule Sheet data" for details.

In the activity setup performed by the Administrator, one of more WBS Codes can be associated with an activity. The value carried by the Total Cost data element on add to a Schedule Activity Attribute form gets passed onto these WBS codes as the result of calculations such as data roll up to a Cost Sheet, or earned value calculations. The logic used by the Activity Cost 1 and Activity Cost 2 and the associated Activity Total Cost 1 Per WBS and Activity Total Cost 2 Per WBS data elements is based on the association of an activity to a WBS code.

The values for Activity Total Cost 1 Per WBS and Activity Total Cost 2 Per WBS data elements are calculated by the system based on the corresponding Activity Cost 1 or Activity Cost 2 data element values.

These are the steps the system follows to calculate values for Activity Total Cost 1 Per WBS and Activity Total Cost 2 Per WBS data elements:

1 If the combination of Cost and Per WBS data elements are used on an Schedule Activity Attribute form, the system will scan through all of the activities and associated WBS codes.
2 The system will accumulate all of the values in the Activity Cost 1 or Activity Cost 2 data elements for all activities per WBS code associated with each activity.
3 Use the total value calculated in step 2 per WBS code as the value for each Activity Total Cost 1 Per WBS and Activity Total Cost 2 Per WBS data element specified for each activity.
4 Each activity gets a total value calculated in step 2 based on the WBS code associated with it.

The following example explains these calculations. For this example, the data elements Activity Cost 1 and Activity Total Cost 1 Per WBS have been added to the attribute form:

Activity Name

Activity Cost 1

Activity Total Cost 1 Per WBS

Control Account 1

$28,000.00

 

Control Activity 1.1

$19,000.00

Control Point 1.1.1

$10,000.00

$28,000.00

WBS - 1

$10,000.00

 

Control Point 1.1.2

$9,000.00

$28,000.00

WBS - 1

$9,000.00

 

Control Activity 1.2

$9,000.00

Control Point 1.2.1

$5,000.00

$28,000.00

WBS - 1

$5,000.00

 

Control Point 1.2.2

$4,000.00

$28,000.00

WBS - 1

$4,000.00

 

Control Account 2

$20,000.00

Control Activity 2.1

$20,000.00

Control Point 2.1.1

$8,000.00

$20,000.00

WBS - 2

$8,000.00

 

Control Point 2.1.2

$12,000.00

$20,000.00

WBS - 2

$12,000.00

 

In the above example, Control Point 1.1.1 has a value $28000.00, which was arrived at by adding the value of WBS - 1 across all activities.

 

 

 

 