If the Schedule Attribute form includes an Activity Earned Value Filter field (uuu_activity_ev_filter), you can set up progress filtering for earned value sheets in the Cost Manager.
To set up the schedule sheet for progress filtering
1 | Open a schedule sheet in a template or project/shell. |
2 | Add the Activity Earned Value Filter data element as a column to the schedule sheet. |
3 | Enter an alphanumeric value, such as “progressable” or “non-progressable,” into the column cell. (Use whatever term you like.) |
4 | Save the schedule sheet. |