About scope management data elements

There are data elements that are specific to scope management, which were added to the schedule attribute form in Primavera uDesigner. These data elements can be added to the scope management schedule sheet as columns as you work with the sheet. If data elements are on both the schedule attribute form and on the BP that you will be using to execute the activity task for scope management, the values are copied from the form to the BP and vice versa.

When you are planning to use scope management, consult with the Primavera uDesigner user and your company administrator to achieve the setup of data elements and BPs that will meet your business needs for managing scope.

The scope management-specific data elements that are added to the schedule attribute form are:

Data Element Name

Description

Actual Start Date

Actual start date of the activity.

Actual Finish Date

Actual finish date of the activity.

Actual Duration

Actual duration of the activity. This is calculated from the Actual Start Date and Actual Finish Date.

Status

Activity status. The default is Not Started.

Predecessors

A list of the predecessor activities.

Note: Activities that have no predecessors are known as floating activities.

Record Number

Hyperlink to the linked BP record.

Record Status

Hyperlink to the linked BP record.

Estimated Start Date

Calculated date.

Estimated Finish Date

Calculated date.

Estimated Duration

Calculated duration.

Auto-update Activity Data

Enables the automatic update of activity data. The default is unchecked. If this checkbox is not selected, the activity must be completed manually, and automatic completion will be turned off. This means you must change the activity status to compete and enter an actual finish date.

Linked BP Name

Name of the linked BP.

 

 

 

 