Automatic activity status transitions

When activities are auto-controlled (the Auto-update Activity Status box is checked), activity status is read only. The statuses automatically transition as follows:

1 Not started (default)
2 In progress (this is when the linked BP is launched)
3 Complete (when the BP completion conditions are met)

 

 

 

 