For BPs to launch automatically from activities, these conditions must be met:
• | Auto-control must be set to On on the Schedule Sheet properties |
• | Activity is not manually controlled, which means that Auto-update Activity is selected |
• | Activity has a BP setup |
• | Activity has the status Not Started |
• | Activity is floating (no predecessors) or the predecessors are all in Complete status |
• | The start date for the activity is not in the future |