Automatic launching of business processes

For BPs to launch automatically from activities, these conditions must be met:

Auto-control must be set to On on the Schedule Sheet properties
Activity is not manually controlled, which means that Auto-update Activity is selected
Activity has a BP setup
Activity has the status Not Started
Activity is floating (no predecessors) or the predecessors are all in Complete status
The start date for the activity is not in the future

 

 

 

 