Impact of Successor and Predecessor Activities on Launching and Completion of BPs

This section discusses the interaction of activities and the launching of BPs. The start of an activity is affected by whether there is a lag or a lead, as shown in the examples below.

 

Finish-to-start (FS)

Start-to-start (SS)

Finish-to-finish (FF) and start-to-finish (SF)

 

 

 