Scope Management functionality can be enabled on any schedule sheet (including master schedule sheets). You can modify the properties associated with scope management. These include:
• | Auto-control |
• | Schedule start date |
• | Error notification to users and groups |
To manage scope management properties
1 | In User Mode, navigate to the project or shell Schedule Manager and select Schedule Log. The Schedule Sheets log opens. |
2 | Select a schedule sheet and click Properties. |
3 | On the General tab, complete or modify the fields described in the following table and then click OK. |
In this field: |
Do this: |
Auto-control |
Controls the automatic update of tasks. The default is Off. Setting auto-control to On enables the automatic launch of BP records. Setting auto-control to Off means that BPs will not be launched automatically on activities and completion conditions will not be checked on activities. Users can still launch BPs manually. Note: Unifier disregards predecessor/successor dependency relationships when you manually start an activity, even if auto-control is set to On in the schedule sheet properties. |
Schedule Start Date |
Drives the dates of floating activities on the schedule sheet. Activities cannot begin before this date, unless their preceding activities complete previous to this date. |
Notify users and/or groups on errors |
Select users and groups to be notified if there are errors during the scope management task routing. |