Manage scope management properties

Scope Management functionality can be enabled on any schedule sheet (including master schedule sheets). You can modify the properties associated with scope management. These include:

Auto-control
Schedule start date
Error notification to users and groups

To manage scope management properties

1 In User Mode, navigate to the project or shell Schedule Manager and select Schedule Log. The Schedule Sheets log opens.
2 Select a schedule sheet and click Properties.
3 On the General tab, complete or modify the fields described in the following table and then click OK.

 

In this field:

Do this:

Auto-control

Controls the automatic update of tasks. The default is Off. Setting auto-control to On enables the automatic launch of BP records. Setting auto-control to Off means that BPs will not be launched automatically on activities and completion conditions will not be checked on activities. Users can still launch BPs manually.

Note: Unifier disregards predecessor/successor dependency relationships when you manually start an activity, even if auto-control is set to On in the schedule sheet properties.

Schedule Start Date

Drives the dates of floating activities on the schedule sheet. Activities cannot begin before this date, unless their preceding activities complete previous to this date.

Notify users and/or groups on errors

Select users and groups to be notified if there are errors during the scope management task routing.

 

 

 

 


Oracle Corporation

Primavera Unifier 9.10 • Copyright © 1998, 2012, Oracle and/or its affiliates. All rights reserved.

Copyright Information