Update activity properties

To update activity properties for scope management

1 In User Mode, navigate to the Schedule Manager and select Schedule Log. The Schedule Sheets log opens.
2 Select a schedule sheet and click the Open button.
3 Click the link for an activity. The Activity Properties window displays.
4 Modify the activity properties as needed. The properties shown in the Activity Properties window depend on the design configured in Primavera uDesigner. Activity properties associated with scope management can include:

 

Property Name

Definition

Activity Statuses

Read-only for automatically controlled activities. Editable for manually controlled activities. The statuses are:

Not Started: All activities have this as the initial status by default. Indicates that the BP linked to the activity has not yet been launched.
In Progress: Indicates that predecessor activities are complete and that the current activity is not started. A new BP record is created and linked to the activity.

Note: You cannot modify certain activity attributes while an activity is In progress.

Complete: Indicates that an activity is complete based on the completion conditions set up for the activity.

Linked BP Name

Read-only; displays the BP linked to the activity.

Record Number

Read-only; displays the current record number that is linked with the activity.

Record Status

Read-only; displays the current status of the BP record linked to the activity.

Actual Start Date

Read-only or editable, depending on the setting for the Auto-update activity data box. This value is set when the linked BP is launched for the activity.

Actual Finish Date

Read-only or editable, depending on the setting for the Auto-update activity data box. This value is set when the linked BP is completed based on the completion conditions.

Estimated Start Date

Read-only; indicates the estimated start date for the activity.

Estimated Finish Date

Read-only, indicates the estimated finish date for the activity.

Auto-update activity status

The default is not selected. Indicates if the current activity is automatically controlled or manually controlled.

Dependencies

Read-only; lists the predecessor activities for the current activity using a coding format indicating lag and lead time: Finish to Start (FS), Start to Start (SS), Finish to Finish (FF), and Start to Finish (SF). For example:

3FS + 3d (Activity 3 is a predecessor with FS relationship with 3 days lag)
2SS - 1d (Activity 2 is a predecessor with SS relationship with a 1 day lead)

An activity can have multiple dependencies separated by a comma. The value is updated every time there is an addition or change to the predecessors.

5 Click OK.

 

 

 

 