This figure shows the required task order for the single server upgrade method. In this method, the upgrade tasks are performed in numerical order.

  1. Task 1 — Record 1.0.x Settings

  2. Task 2 — Dump 1.0.x Database (STA Server #1)

  3. Task 3 — Transfer 1.0.x Database (STA Server #1 to Backup Server)

  4. Task 4 — Install Linux 6.x (STA Server #1)

  5. Task 5 — Install STA 2.0 (STA Server #1)

  6. Task 6 — Dump New 2.0 Database (STA Server #1)

  7. Task 7 — Transfer 1.0.x Database (Backup Server to STA Server #1)

  8. Task 8 — Process/load 1.0.x Database (STA Server #1)

  9. Task 9 — Upgrade Database (STA Server #1)

  10. Task 10 — Configure STA 2.0