Setting Overtime Policy

Previous TopicNext TopicContents

To set overtime policy, which enables users to enter overtime in their timesheets:

  1. Click Resources.
  2. On the Resources navigation bar, click Administration.
  3. On the Administration page, click the Resources tab.
  4. On the Resources tab, click the Settings detail window.
  5. In the Settings detail window, select the Overtime Allowed option.
  6. In the Overtime Factor field, type the overtime factor by which the resource’s standard price is multiplied to determine the overtime price (standard price * overtime factor = overtime price).

    Note: In P6 Progress Reporter, resources indicate overtime with a slash (/) in the time field. For example, if a resource worked 10 hours in one eight-hour day, the user types 8/2 for that day. In P6, resources can enter overtime using separate overtime fields.

Related Topics

Configuring Resources to Use P6 Progress Reporter

Creating User Accounts for P6 EPPM

Assigning Associated Resources

Configuring Resource Settings for Timesheet Reporting



Legal Notices
Copyright © 1999, 2014, Oracle and/or its affiliates. All rights reserved.

Last Published Wednesday, February 19, 2014

PDF Library