You can mark multiple tasks complete. Updating multiple tasks simultaneously is faster than marking tasks complete one at a time. However, you should avoid marking tasks complete by mistake since you cannot remove the Finished date from tasks marked complete.
Note: Contact your manager or administrator if you need to restore data that you cannot edit. For example, if you mark multiple tasks complete and then discover that they were marked complete by mistake or that additional work effort is required, your manager can use P6 to manually remove the finish date.
To mark multiple tasks complete:
Note: You cannot set Finished dates when marking multiple tasks complete at once. The Finished date for the tasks will be the date on which you marked them complete.