Completing Tasks
After you have marked a task as started and updated its progress to reflect work performed, you can mark it as complete to indicate that your work on the task is finished.
To mark a task as complete:
- On the Task List, tap the task you want to update.
- Tap Mark Task Complete.
- Tap Save to accept the default Finished value. To select another actual finish date, adjust the time controls, if enabled, before you tap Save.
Notes:
- When you mark a task as complete, any Time Left will automatically be added to the Time Spent.
- You cannot remove the finish date after you tap Save. Contact your manager or administrator if you need to restore data that you cannot edit.