When a project is locked, no direct changes can be made to the project. For example, project team members cannot update their status or finance analysts cannot update project budget. Project managers can lock an active project if they do not want any changes to be made to the project. Projects that are complete can also be locked to prevent further updates from being made. The project lock status is displayed on the project Import/Export page. If a project is On-Hold, you can only perform a Read-Only Export.
The following items are editable when a project is locked:
You can perform limited editing on the following items when the project is locked.
Entity | Locked | Allowed |
---|---|---|
Roadmap | All sections are read-only. |
|
Dates | All sections are read-only. |
|
Team—Resources | Most sections are locked. | You can add new team members. |
Team—Allocation | You cannot release an allocation slot as it can result in deleting a team member. | You can edit the other sections. |
Project Finances | Settings page is locked. | You can edit the other sections. |
Allocation Approvals | Approvals that can result in deletions of team members. | You can edit the other sections. |
Documents | The documents that are referenced in the activities are locked. | All other documents can be edited. |
During MS Project Import/Export
Data Mapping for EnterpriseTrack and MS Project
Legal Notices