ET Field | MS Project Field |
---|---|
Currency Symbol | Symbol |
Positive Currency Format | Placement X
|
Number of Decimal Places | Decimal digits |
ET Activity Schedule Mode | MS Project Task Type |
---|---|
Duration and % resource availability |
Fixed Duration - non effort driven |
Effort at activity level - Equal distribution | Fixed Work |
Effort at activity level - Unequal distribution | Fixed Work |
Effort at resource level (Summary) | Fixed Work |
Effort at resource level (Detailed) | Fixed Work |
Note: Scheduling Mode in EnterpriseTrack maps to Task Type in MS Project.
ET Field | MS Project Field |
---|---|
Work Hours Per Day | Hours per day |
Work Hours Per Week
| Hours per week |
Start Fiscal Year | Fiscal year starts in |
ET Field | MS Project Field |
---|---|
Project Name | Title |
Comments | Comments |
Default Project Calendar | Calendar |
ET Field | MS Project Field |
---|---|
Team Member rate | Rate based (standard or overtime) |
Equipment rate |
Material (rate based) |
Cost-planned_fixed | Fixed Cost |
cost- planned_material | N/A |
cost - actual_material | N/A |
ET Field | MS Project Field |
---|---|
Et_tm_id | Text30 |
ET_user_id | Text29 |
ET_role_id | Text28 |
ET_role_name | Text27 |
ET_1nameET_fname | Name |
Resource type (person or equipment) | Type (work= person or equipment) |
Resource calendar | Resource Calendar |
ET Field | MS Project Field |
---|---|
Baseline_start_date | Baseline Start |
Baseline_completion_date | Baseline Completion |
Baseline_duration | Baseline Duration |
Planned_completion_date | N/A |
Planned_duration | Duration |
Actual_start_date |
Start |
Actual_completion_date | N/A |
Actual_duration | Actual Duration |
Planned_duration | N/A |
Actual_duration | N/A |
ET Field | MS Project Field |
---|---|
Name | Name |
Comments | Notes |
Activity_id | Text30 |
% completion | % completion |
Owners | Owner |
Activity marked NA | Text29 is set to NA_Closed |
WBS Code | WBS |
Milestone | Milestone |
Critical tasks | Tasks are critical if slack is less than or equal to 0 days. |
Notes:
Data Mapping for EnterpriseTrack and MS Project
Data Mapping During EnterpriseTrack Import