MS Project Task Type | ET Activity Schedule Mode |
---|---|
Fixed Duration - non effort driven |
Duration and % resource availability |
Fixed Work | Effort at activity level - Equal distribution |
Fixed Work | Effort at activity level - Unequal distribution |
Fixed Work | Effort at resource level (Summary) |
Fixed Work | Effort at resource level (Detailed) |
Note: Scheduling Mode in EnterpriseTrack maps to Task Type in MS Project.
MS Project Field | ET Field |
---|---|
Hours per day | Work Hours Per Day |
Hours per week
| Work Hours Per Week |
Fiscal year starts in | Start Fiscal Year |
MS Project Field | ET Field |
---|---|
Fixed Cost | Planned_non_resource_fixed_cost |
Actual Cost | Actual_non_resource_fixed_cost |
Cost | Planned_non_resource_material_cost |
Actual Cost | Actual_non_resource_material_cost |
Cost | Planned_non_resource_other_cost |
Actual Cost | Actual_non_resource_other_cost |
Notes:
MS Project Field | ET Field |
---|---|
Baseline start | Activity dates -baseline_start_date |
Baseline Completion | Activity dates -baseline_completion_date |
Baseline start | Activity dates- baseline duration |
Start | Activity dates- planned start date |
Finish | Activity dates - planned completion date |
Plan duration of task | Activity dates- planned duration |
Start date of task | Activity dates - actual start date |
Actual finish of task | Activity dates-actual completion date |
Actual duration of task | Activity dates- actual duration |
Plan duration of task | Owner dates- planned duration |
Actual duration of task | Owner dates-actual duration |
% Complete of task | Percent_completion |
Actual work (of resource) | Actual_total_effort |
Work (of task) | Planned_total_effort |
N/A | Baseline_effort |
Data Mapping for EnterpriseTrack and MS Project
Data Mapping During EnterpriseTrack Export
Legal Notices
Copyright © 2000, 2016,
Oracle and/or its affiliates. All rights reserved.
Last Published Tuesday, June 21, 2016