Reassigning an Activity

To reassign the activities associated with a role:

  1. Navigate to the Project Resources page by selecting (Project #)> Go To> Resources > Listing or by clicking the Resources link on the Left Navigation Bar within a particular project. The Project Resources page is displayed.
  2. Select a project role. From the Actions menu, select Reassign Activities.
  3. For each activity, from the Reassignment drop-down menu, select a resource.
  4. Click Reassign.

See Also

Working with Project Resources

Assigning Resources to a Project

Re-assigning a Team Member to a Role

Reassigning a Team Member

Edit Team Member Information

View Rate Change History

Using the EnterpriseTrack Email client

Using an External Email Client

Managing Your Team Picture

Deleting a Team Picture

Working with Resource Assignments

Create Request for Resource Allocation

Edit a Resource Allocation Request

Withdraw a Request for Resource Allocation

Reopen Resource Allocation Request

Release Project Resource Allocation

View a Team Member's Calendar



Legal Notices
Copyright © 2000, 2016, Oracle and/or its affiliates. All rights reserved.

Last Published Wednesday, November 30, 2016