View a Monte Carlo Project Result
get
/api/restapi/monteCarloProjectResult/{monteCarloProjectResultId}
This endpoint returns Monte Carlo project results that meet the following requirements:
- The object has an ID that matches the value of the {monteCarloProjectResultId} path parameter.
Request
Path Parameters
-
monteCarloProjectResultId(required): integer(int64)
ID of MonteCarlo Project Result to be found.
There's no request body for this operation.
Back to TopResponse
Supported Media Types
- application/json
200 Response
Successful operation
Root Schema : ApiEntityMonteCarloProjectResult
Type:
object
Title:
Show Source
ApiEntityMonteCarloProjectResult
-
deterministicDurationProbability: number
(double)
Read Only:
true
The probability of the project's remaining duration being less than or equal to the project remaining duration, calculated using fixed duration and date values. -
deterministicFinishProbability: number
(double)
Read Only:
true
The probability of the project finishing on or before the deterministic finish date. -
deterministicStartProbability: number
(double)
Read Only:
true
The probability of the project starting on or before the deterministic start date. -
durationStdDeviation: number
(double)
Read Only:
true
How much the variation of remaining durations deviates from the calculated mean remaining duration. -
durationVariance: number
Read Only:
true
Variance between project remaining hours in a Monte Carlo analysis result. -
finishStdDeviation: number
(double)
Read Only:
true
How much the project finish dates deviate from the calculated mean finish date. -
finishVariance: number
Read Only:
true
Variance between project finish dates in a Monte Carlo analysis result. -
link: string
(url)
Read Only:
true
The self-link to the object. This field is populated only in the responses generated by the batch create APIs. -
maxDuration: number
(double)
Read Only:
true
The maximum project remaining duration sampled during the risk analysis. -
maxFinishDate: string
(date-time)
Read Only:
true
The latest project finish date sampled during the risk analysis. -
maxStartDate: string
(date-time)
Read Only:
true
The latest project start date sampled during the risk analysis. -
meanDuration: number
(double)
Read Only:
true
The average project remaining duration sampled during risk analysis. -
meanFinish: string
(date-time)
Read Only:
true
The average project finish date sampled during the risk analysis. -
meanStart: string
(date-time)
Read Only:
true
The average project start date sampled during the risk analysis. -
minDuration: number
(double)
Read Only:
true
The minimum project remaining duration sampled during the risk analysis. -
minFinishDate: string
(date-time)
Read Only:
true
The earliest project finish date sampled during the risk analysis. -
minStartDate: string
(date-time)
Read Only:
true
The earliest project start date sampled during the risk analysis. -
monteCarloProjectResultFinancial:
monteCarloProjectResultFinancial
An object containing Monte Carlo project result financial fields in the form of key-value pairs.
-
monteCarloProjectResultId: integer
(int64)
Read Only:
true
The unique identifier of a project Monte Carlo analysis result. -
monteCarloScenario: string
Read Only:
true
Allowed Values:[ "PRE_MITIGATED", "POST_MITIGATED" ]
The type of risk analysis run on a project.- PRE_MITIGATED : A quantitative risk analysis that doesn't take into account the impact of defined risk response plans.
- POST_MITIGATED : A quantitative risk analysis that takes into account the impact of defined risk response plans.
-
optimisticDuration: number
(double)
Read Only:
true
The optimistic remaining duration calculated using the optimistic percentile. -
optimisticFinishDate: string
(date-time)
Read Only:
true
The calculated project finish date that corresponds to the defined optimistic percentile. -
optimisticStartDate: string
(date-time)
Read Only:
true
The calculated project start date that corresponds to the defined optimistic percentile. -
p50Duration: number
(double)
Read Only:
true
The calculated median remaining duration. -
p50FinishDate: string
(date-time)
Read Only:
true
The calculated project finish date that corresponds to the P50 or median percentile. -
p50StartDate: string
(date-time)
Read Only:
true
The calculated project start date that corresponds to the P50 or median percentile. -
pessimisticDuration: number
(double)
Read Only:
true
The pessimistic remaining duration calculated using the pessimistic percentile. -
pessimisticDurationContingency: number
(double)
Read Only:
true
The difference between the project pessimistic percentile remaining duration and the project deterministic remaining duration. -
pessimisticFinishContingency: number
(double)
Read Only:
true
The difference between the project pessimistic percentile finish date and the project deterministic finish date. -
pessimisticFinishDate: string
(date-time)
Read Only:
true
The calculated project finish date that corresponds to the defined pessimistic percentile. -
pessimisticStartContingency: number
(double)
Read Only:
true
The difference between the project pessimistic percentile start date and the project deterministic start date. -
pessimisticStartDate: string
(date-time)
Read Only:
true
The calculated project start date that corresponds to the defined pessimistic percentile. -
projectId: integer
(int64)
The unique identifier of a project.
-
removedItemId: integer
(int64)
Read Only:
true
The unique identifier of a removed Monte Carlo item. -
removedItemType: string
Read Only:
true
Allowed Values:[ "ACTIVITY_UNCERTAINTY", "NONE", "RISK" ]
The type of a removed item. -
startStdDeviation: number
(double)
Read Only:
true
How much the variation of project start dates deviate from the calculated mean start date. -
startVariance: number
Read Only:
true
Variance between project start dates in a Monte Carlo analysis result. -
totalMeanDelay: number
(double)
Read Only:
true
The average project delay duration sampled during the risk analysis.
Calculated as Mean Remaining Duration minus Project Remaining Duration. -
totalMeanDelayPercent: number
(double)
Read Only:
true
The average delay percentage of the remaining duration for the project.
Calculated as Project Mean Delay divided by Project Remaining Duration multiplied by 100. -
totalUncertaintyMeanDelay: number
(double)
Read Only:
true
The total uncertainty mean delay contained in a Monte Carlo analysis result. -
updateDate: string
(date-time)
Read Only:
true
Date when the record was last updated.
Nested Schema : monteCarloProjectResultFinancial
An object containing Monte Carlo project result financial fields in the form of key-value pairs.
Match All
Show Source
-
object
ApiEntityMonteCarloProjectResultFinancial
Title:
ApiEntityMonteCarloProjectResultFinancial
Nested Schema : ApiEntityMonteCarloProjectResultFinancial
Type:
object
Title:
Show Source
ApiEntityMonteCarloProjectResultFinancial
-
atCompletionCostStdDeviation: number
(double)
Read Only:
true
How much the distribution of sampled project costs deviates from the calculated mean project cost. -
atCompletionCostVariance: number
Read Only:
true
The project at-completion cost variance. -
costStdDeviation: number
(double)
Read Only:
true
How much the distribution of sampled project costs deviates from the calculated mean project cost. -
costVariance: number
Read Only:
true
The measure of project cost performance sampled during a risk analysis. It is calculated as the difference between the project's actual cost and the planned cost. -
deterministicAtCompletionCostProbability: number
(double)
Read Only:
true
The probability of achieving the project deterministic at-completion cost. -
deterministicCostProbability: number
(double)
Read Only:
true
The probability of achieving the project deterministic remaining cost. -
link: string
(url)
Read Only:
true
The self-link to the object. This field is populated only in the responses generated by the batch create APIs. -
maxCost: number
(double)
Read Only:
true
The maximum project remaining cost sampled during the risk analysis. -
maximumAtCompletionCost: number
(double)
Read Only:
true
The maximum project at-completion cost sampled during the risk analysis. -
meanAtCompletionCost: number
(double)
Read Only:
true
The average project cost sampled during the risk analysis. -
meanCost: number
(double)
Read Only:
true
The average project cost sampled during the risk analysis. -
minCost: number
(double)
Read Only:
true
The minimum project remaining cost sampled during the risk analysis. -
minimumAtCompletionCost: number
(double)
Read Only:
true
The minimum project at-completion cost sampled during the risk analysis. -
monteCarloProjectResultId: integer
(int64)
Read Only:
true
The unique identifier of the cost of the result of a Monte Carlo project analysis. -
optimisticAtCompletionCost: number
(double)
Read Only:
true
The optimistic at-completion cost sampled during the risk analysis. -
optimisticCost: number
(double)
Read Only:
true
The optimistic remaining cost sampled during the risk analysis. -
p50AtCompletionCost: number
(double)
Read Only:
true
The P50 or median at-completion cost sampled during the risk analysis. -
p50Cost: number
(double)
Read Only:
true
The P50 or median remaining cost sampled during the risk analysis. -
pessimisticAtCompletionCost: number
(double)
Read Only:
true
The pessimistic at-completion cost calculated using the pessimistic percentile. -
pessimisticAtCompletionCostContingency: number
(double)
Read Only:
true
The difference between the project pessimistic at-completion cost and the project deterministic at-completion cost. -
pessimisticCost: number
(double)
Read Only:
true
The pessimistic remaining cost calculated using the pessimistic percentile. -
pessimisticCostContingency: number
(double)
Read Only:
true
The difference between the project pessimistic remaining cost and the project deterministic remaining cost. -
totalAtCompletionMeanCostImpact: number
(double)
Read Only:
true
Mean cost increase of the project. -
totalAtCompletionMeanCostImpactPercent: number
(double)
Read Only:
true
Percentage mean cost increase of the project. -
totalMeanCostImpact: number
(double)
Read Only:
true
The estimated average project cost impact before implementing a response action. -
totalMeanCostImpactPercent: number
(double)
Read Only:
true
The estimated average project cost impact before implementing a response action represented as a percent. -
updateDate: string
(date-time)
Read Only:
true
Date when the record was last updated.
404 Response
The requested Monte Carlo project result does not exist, or you do not have access to it.