View a Monte Carlo Project Result by Project and Scenario
get
/api/restapi/monteCarloProjectResult/project/{projectId}/scenario/{scenario}
This endpoint returns a Monte Carlo project results that meet the following requirements:
- The object is associated with a project with an ID value that matches the value of the {projectId} path parameter.
- The object was run under a scenario that matches the value of the {scenario} path parameter.
Request
Path Parameters
-
projectId(required): integer(int64)
Project ID of which MonteCarlo Project Result has to be returned.
-
scenario(required): string
The type of risk analysis run on a project.
- PRE_MITIGATED : A quantitative risk analysis that doesn't take into account the impact of defined risk response plans.
- POST_MITIGATED : A quantitative risk analysis that takes into account the impact of defined risk response plans.
- BOTH : A quantitative risk analysis that uses both pre and post mitigated contexts.
Allowed Values:[ "PRE_MITIGATED", "POST_MITIGATED", "BOTH" ]
There's no request body for this operation.
Back to TopResponse
Supported Media Types
- application/json
200 Response
Successful operation
Root Schema : List<ApiEntityMonteCarloProjectResult>
Type:
array
Title:
Show Source
List<ApiEntityMonteCarloProjectResult>
-
Array of:
object ApiEntityMonteCarloProjectResult
Title:
ApiEntityMonteCarloProjectResult
Nested Schema : ApiEntityMonteCarloProjectResult
Type:
object
Title:
Show Source
ApiEntityMonteCarloProjectResult
-
deterministicDurationProbability: number
(double)
Read Only:
true
The probability of the project's remaining duration being less than or equal to the project remaining duration, calculated using fixed duration and date values. -
deterministicFinishProbability: number
(double)
Read Only:
true
The probability of the project finishing on or before the deterministic finish date. -
deterministicStartProbability: number
(double)
Read Only:
true
The probability of the project starting on or before the deterministic start date. -
durationStdDeviation: number
(double)
Read Only:
true
How much the variation of remaining durations deviates from the calculated mean remaining duration. -
durationVariance: number
Read Only:
true
Variance between project remaining hours in a Monte Carlo analysis result. -
finishStdDeviation: number
(double)
Read Only:
true
How much the project finish dates deviate from the calculated mean finish date. -
finishVariance: number
Read Only:
true
Variance between project finish dates in a Monte Carlo analysis result. -
link: string
(url)
Read Only:
true
The self-link to the object. This field is populated only in the responses generated by the batch create APIs. -
maxDuration: number
(double)
Read Only:
true
The maximum project remaining duration sampled during the risk analysis. -
maxFinishDate: string
(date-time)
Read Only:
true
The latest project finish date sampled during the risk analysis. -
maxStartDate: string
(date-time)
Read Only:
true
The latest project start date sampled during the risk analysis. -
meanDuration: number
(double)
Read Only:
true
The average project remaining duration sampled during risk analysis. -
meanFinish: string
(date-time)
Read Only:
true
The average project finish date sampled during the risk analysis. -
meanStart: string
(date-time)
Read Only:
true
The average project start date sampled during the risk analysis. -
minDuration: number
(double)
Read Only:
true
The minimum project remaining duration sampled during the risk analysis. -
minFinishDate: string
(date-time)
Read Only:
true
The earliest project finish date sampled during the risk analysis. -
minStartDate: string
(date-time)
Read Only:
true
The earliest project start date sampled during the risk analysis. -
monteCarloProjectResultFinancial:
monteCarloProjectResultFinancial
An object containing Monte Carlo project result financial fields in the form of key-value pairs.
-
monteCarloProjectResultId: integer
(int64)
Read Only:
true
The unique identifier of a project Monte Carlo analysis result. -
monteCarloScenario: string
Read Only:
true
Allowed Values:[ "PRE_MITIGATED", "POST_MITIGATED" ]
The type of risk analysis run on a project.- PRE_MITIGATED : A quantitative risk analysis that doesn't take into account the impact of defined risk response plans.
- POST_MITIGATED : A quantitative risk analysis that takes into account the impact of defined risk response plans.
-
optimisticDuration: number
(double)
Read Only:
true
The optimistic remaining duration calculated using the optimistic percentile. -
optimisticFinishDate: string
(date-time)
Read Only:
true
The calculated project finish date that corresponds to the defined optimistic percentile. -
optimisticStartDate: string
(date-time)
Read Only:
true
The calculated project start date that corresponds to the defined optimistic percentile. -
p50Duration: number
(double)
Read Only:
true
The calculated median remaining duration. -
p50FinishDate: string
(date-time)
Read Only:
true
The calculated project finish date that corresponds to the P50 or median percentile. -
p50StartDate: string
(date-time)
Read Only:
true
The calculated project start date that corresponds to the P50 or median percentile. -
pessimisticDuration: number
(double)
Read Only:
true
The pessimistic remaining duration calculated using the pessimistic percentile. -
pessimisticDurationContingency: number
(double)
Read Only:
true
The difference between the project pessimistic percentile remaining duration and the project deterministic remaining duration. -
pessimisticFinishContingency: number
(double)
Read Only:
true
The difference between the project pessimistic percentile finish date and the project deterministic finish date. -
pessimisticFinishDate: string
(date-time)
Read Only:
true
The calculated project finish date that corresponds to the defined pessimistic percentile. -
pessimisticStartContingency: number
(double)
Read Only:
true
The difference between the project pessimistic percentile start date and the project deterministic start date. -
pessimisticStartDate: string
(date-time)
Read Only:
true
The calculated project start date that corresponds to the defined pessimistic percentile. -
projectId: integer
(int64)
The unique identifier of a project.
-
removedItemId: integer
(int64)
Read Only:
true
The unique identifier of a removed Monte Carlo item. -
removedItemType: string
Read Only:
true
Allowed Values:[ "ACTIVITY_UNCERTAINTY", "NONE", "RISK" ]
The type of a removed item. -
startStdDeviation: number
(double)
Read Only:
true
How much the variation of project start dates deviate from the calculated mean start date. -
startVariance: number
Read Only:
true
Variance between project start dates in a Monte Carlo analysis result. -
totalMeanDelay: number
(double)
Read Only:
true
The average project delay duration sampled during the risk analysis.
Calculated as Mean Remaining Duration minus Project Remaining Duration. -
totalMeanDelayPercent: number
(double)
Read Only:
true
The average delay percentage of the remaining duration for the project.
Calculated as Project Mean Delay divided by Project Remaining Duration multiplied by 100. -
totalUncertaintyMeanDelay: number
(double)
Read Only:
true
The total uncertainty mean delay contained in a Monte Carlo analysis result. -
updateDate: string
(date-time)
Read Only:
true
Date when the record was last updated.
Nested Schema : monteCarloProjectResultFinancial
An object containing Monte Carlo project result financial fields in the form of key-value pairs.
Match All
Show Source
-
object
ApiEntityMonteCarloProjectResultFinancial
Title:
ApiEntityMonteCarloProjectResultFinancial
Nested Schema : ApiEntityMonteCarloProjectResultFinancial
Type:
object
Title:
Show Source
ApiEntityMonteCarloProjectResultFinancial
-
atCompletionCostStdDeviation: number
(double)
Read Only:
true
How much the distribution of sampled project costs deviates from the calculated mean project cost. -
atCompletionCostVariance: number
Read Only:
true
The project at-completion cost variance. -
costStdDeviation: number
(double)
Read Only:
true
How much the distribution of sampled project costs deviates from the calculated mean project cost. -
costVariance: number
Read Only:
true
The measure of project cost performance sampled during a risk analysis. It is calculated as the difference between the project's actual cost and the planned cost. -
deterministicAtCompletionCostProbability: number
(double)
Read Only:
true
The probability of achieving the project deterministic at-completion cost. -
deterministicCostProbability: number
(double)
Read Only:
true
The probability of achieving the project deterministic remaining cost. -
link: string
(url)
Read Only:
true
The self-link to the object. This field is populated only in the responses generated by the batch create APIs. -
maxCost: number
(double)
Read Only:
true
The maximum project remaining cost sampled during the risk analysis. -
maximumAtCompletionCost: number
(double)
Read Only:
true
The maximum project at-completion cost sampled during the risk analysis. -
meanAtCompletionCost: number
(double)
Read Only:
true
The average project cost sampled during the risk analysis. -
meanCost: number
(double)
Read Only:
true
The average project cost sampled during the risk analysis. -
minCost: number
(double)
Read Only:
true
The minimum project remaining cost sampled during the risk analysis. -
minimumAtCompletionCost: number
(double)
Read Only:
true
The minimum project at-completion cost sampled during the risk analysis. -
monteCarloProjectResultId: integer
(int64)
Read Only:
true
The unique identifier of the cost of the result of a Monte Carlo project analysis. -
optimisticAtCompletionCost: number
(double)
Read Only:
true
The optimistic at-completion cost sampled during the risk analysis. -
optimisticCost: number
(double)
Read Only:
true
The optimistic remaining cost sampled during the risk analysis. -
p50AtCompletionCost: number
(double)
Read Only:
true
The P50 or median at-completion cost sampled during the risk analysis. -
p50Cost: number
(double)
Read Only:
true
The P50 or median remaining cost sampled during the risk analysis. -
pessimisticAtCompletionCost: number
(double)
Read Only:
true
The pessimistic at-completion cost calculated using the pessimistic percentile. -
pessimisticAtCompletionCostContingency: number
(double)
Read Only:
true
The difference between the project pessimistic at-completion cost and the project deterministic at-completion cost. -
pessimisticCost: number
(double)
Read Only:
true
The pessimistic remaining cost calculated using the pessimistic percentile. -
pessimisticCostContingency: number
(double)
Read Only:
true
The difference between the project pessimistic remaining cost and the project deterministic remaining cost. -
totalAtCompletionMeanCostImpact: number
(double)
Read Only:
true
Mean cost increase of the project. -
totalAtCompletionMeanCostImpactPercent: number
(double)
Read Only:
true
Percentage mean cost increase of the project. -
totalMeanCostImpact: number
(double)
Read Only:
true
The estimated average project cost impact before implementing a response action. -
totalMeanCostImpactPercent: number
(double)
Read Only:
true
The estimated average project cost impact before implementing a response action represented as a percent. -
updateDate: string
(date-time)
Read Only:
true
Date when the record was last updated.
204 Response
Successful operation with no content.
404 Response
The requested Monte Carlo project result does not exist, or you do not have access to it.