View Risk Mean Impact Analysis Results

View the average impacts of activities and risks on the project cost and finish date.

To view risk mean impact analysis results:

  1. In the object selector, select a project.
  2. In the sidebar, hover over Risk, and select Risk Analysis.
  3. Select the Mean Impact tab.
  4. In the Response Context list, select an analysis context:
    • Pre-Response: Displays analysis results based on pre-response values.
    • Post-Response: Displays analysis results based on post-response values.
  5. In the Show list, view analysis results for Activity Delay Contribution, Activity Cost Contribution, Risk Delay Contribution, and Risk Cost Contribution.

    Note: Available activity results are determined by your risk analysis settings.

  6. To filter the number of results, select Settings and configure the display options.
  7. Select Show Contribution Breakdown for:
    • Activity Delay Contribution and Activity Cost Contribution to display the impact breakdown by risk.
    • Risk Cost Contribution to display the breakdown by direct cost impact and schedule cost impact.

Tips