View Risk Mean Impact Analysis Results
View the average impacts of activities and risks on the project cost and finish date.
To view risk mean impact analysis results:
- In the object selector, select
Project, select View Projects List, and then select a project name. - From the
Main Menu, select
Risk, and then select Risk Analysis. - In the context bar, select the Risk Analysis
menu, and then select Mean Impact. - In the Response Context list, select an analysis context:
- Pre-Response: Displays analysis results based on pre-response values.
- Post-Response: Displays analysis results based on post-response values.
- In the Show list, select Activity Delay Contribution, Activity Cost Contribution, Risk Delay Contribution, and Risk Cost Contribution.
Note Available activity results are determined by your risk analysis settings.
- Select
Settings for:- Filtering: Filter the number of results displayed.
- View Options: Show result labels as Value, Percentage, or Value and Percentage.
- Select Show Contribution Breakdown to display the following information:
- Activity Delay Contribution and Activity Cost Contribution: Display the direct and indirect impacts by risk, including the contribution value of individual unassigned risks. Unassigned risks are risks that are not assigned to any activities that still impact the project cost, or duration, or both.
- Risk Cost Contribution: Display direct and indirect cost impact and direct and indirect schedule cost impact.
- Review Risk Analysis Run Settings to view the start date, finish date, and duration of the most recently run risk analysis.
Note To view exact risk analysis start and finish times, configure the date format to include time. See Configure the Date Format for more information.
Last Published Monday, October 19, 2026