View Risk Removal Impact Analysis Results

View the risks with the greatest potential impact on project cost and finish date. Use viewing and filtering options to narrow the results in the tornado chart.

Note You must enable the risk removal impact analysis in the analysis settings to view these results. See Run a Risk Analysis for more information.

To view risk removal impact analysis results:

  1. In the object selector, select Project, select View Projects List, and then select a project name.
  2. From the Main Menu, select Risk, and then select Risk Analysis.
  3. In the context bar, select the Risk Analysis menu, and then select Risk Removal Impact.
  4. In the Response Context list, select an analysis context:
    • Pre-Response: Displays analysis results based on pre-response values.
    • Post-Response: Displays analysis results based on post-response values.
  5. To view risk removal impact results for the project cost, select the Remaining Cost tab. To view impact results for the project finish date, select the Finish Date tab.
  6. (Optional) On the Finish Date tab, select a project or milestone in Select Results to view the data on the graph. The Remaining Cost tab only displays data at the project level.

    Select the Group By list to group milestones by project or WBS.

    Collapse Risk Analysis Run Settings to display more Risk Removal Impact results.

  7. Select Settings to configure the following filtering options:
    1. Ignore values smaller than +/-: Enter a minimum percentage value for results to include. The application omits results below that value from the tornado chart.
    2. Show top: Select the number of risks to display, beginning with the highest impact value.
    3. Select Save.

    To exclude a risk from Risk Removal Impact Analysis, select the Exclude from Risk Removal check box on the Risk Register page. The Risk Analysis Run Settings table identifies risks that were manually excluded.

  8. Review Risk Analysis Run Settings to view the start date, finish date, and duration of the most recently run risk analysis.

    Note To view exact risk analysis start and finish times, configure the date format to include time. See Configure the Date Format for more information.