Entering Activity and Assignment Units and Costs

This topic explains the rules for entering unit and cost values at the activity level and resource assignment level.

Units and costs can be defined directly at the activity level if you do not plan to assign resources or roles to your schedule. If assignments exist on the activity, units and costs are entered on individual resource and role assignments. Values entered at the activity level are distributed among assignments with the same type as the activity field. Values entered at the assignment level roll up to the corresponding activity fields.

The cost of your activities is determined by multiplying the amount of work performed, measured in units, and the price of each work unit, measured as a rate. An activity without assignments uses the Default Price/Unit rate set at the project level. An activity with assignments uses the Price/Unit rates of each of its assignments. Because costs and units are interdependent, it is important to be aware that modifying units will recalculate costs and modifying costs will recalculate units. The Calculate Costs from Units setting controls the link between corresponding unit and cost fields. When enabled, costs and units are linked. When disabled, costs and unit values can be edited independent of each other. This setting can be set for each resource and role assignment. At the activity level, the link between costs and units depends on the setting of each of its assignments. When there are no assignments, cost and unit fields are linked.

Entering Activity Units

Units can be entered in the following ways:

Entering Activity Costs

Costs can be entered in the following ways:

Additional Rules: