Link a Work Package to an Activity

Video

Link work packages to activities when you want to manage work package dates using activity dates.

Note: Schedule costs and scope costs are calculated separately. Linking a work package or scope assignment with an activity won't link the costs.

To link an activity to a work package:

  1. Navigate to the Activities page
  2. In the table, select the activity.
  3. On the Layout menu, select Activity Details, and then select the General detail window.
  4. In the Work Package Name field, select a work package.

    Note: You can only link an activity to a work package that belong to the same WBS that is associated with the activity.

  5. All changes made to this page are saved automatically.


Last Published Wednesday, October 16, 2024