Link a Work Package to an Activity
Link work packages to activities when you want to manage work package dates using activity dates.
Note Schedule costs and scope costs are calculated separately. Linking a work package or scope assignment with an activity won't link the costs.
To link an activity to a work package:
- Navigate to the Activities page
- In the object selector, select
Project or
Program, and then select a project or a program from the list.
- From the
Main Menu, select
Schedule, and then select Activities.
- In the object selector, select
- In the table, select the activity.
- On the Layout menu, select
Activity Details, and then select the General detail window.
- In the Work Package Name field, select a work package.
Note You can only link an activity to a work package that belong to the same WBS that is associated with the activity.
- All changes made to this page are saved automatically.