Assigning Resources to an Activity or Task
An owner is assigned to an activity or task from the Roadmap page. To assign a new owner, do the following:
- Select a project and navigate to the Projects roadmap page (Project #) > Go To > Roadmap.
- From the Roadmap page, select the activity or task.
- Select
>Edit > Resources. The resource currently assigned to this activity or task is displayed.
- Assign an existing team member to the activity or click the Add Resource button to add a new resource to this activity or task.
- Choose a project role for the new resource.
- Select a new resource from the drop-down menu. You may only choose from the list of current project team members.
- Enter the Percentage Allocation. You can also choose the role of this resource.
- Accountable (A): Individual who is ultimately responsible for a project with a yes/no authority. One function can have only one accountable person.
- Responsible (R): Individual working on the activity and responsible for action and execution of the plan. The degree of responsibility is usually determined by "A".
- Consult (C): Individual who must be consulted prior to a final decision or action. This involves a two-way communication.
- Inform (I): Individual that needs to know of the decision or action. This is usually a one-way communication.
- Enter the Plan and Actual Percent Availability.
- Enter the Plan Overtime Effort in hours. Planned and actual overtime are part of the total effort and cannot exceed the total effort.
- Total planned effort= Planned standard effort + Planned overtime effort
- Total actual effort = Actual standard effort + Actual overtime effort
- Click the Save button. A new resource is now added to your activity or task.
Note: If the administrator, while creating the activity template, chose to enforce ownership of a task or roadmap by role, only the project manager or users assigned to the chosen roles may be assigned to the task or roadmap. Contact your administrator for details.
Working with Project Activities
Adding a New Activity or Task
Adding a Document to a Roadmap or Task
Uploading a Tool
Working with Project Dependencies
Working with Project Status Indicators
Working with Resource Effort Distribution
Working with Efforts and Dates
About Effort Types
Viewing Finances for an Activity
Modifying an Activity or Task
Activity Approvals
Completing an Activity