Configuring a School Year and Vacation Days

  1. In Reporting and Analytics, click Labor, click Employee Administration, click Admin, and then click School District.
  2. Select a school district, click Edit, and then click the School District Calendars tab.
  3. Click Add, configure the general parameters for the school year, and then click Save.
    1. Select the start and end dates for the school year.
    2. Select the start and end times for a standard school day.
    3. Select the days of the week in a standard school week.
  4. Select the school year, click Edit, and then click the Vacation Days tab.
  5. Add each vacation day or period, and then click Save.
    1. Click Add, and then enter a name.
    2. Select the start and end dates and times for the vacation day or period, and then click Save.