1075 - MTP: Link Bypassed SLT Phase

The link has aligned and may be brought into service without a successful signaling link test (SLT).

Example
RLGHNCXA21W 00-04-18 19:09:14 EST  EAGLE 31.3.0
0140.1075    CARD 1201,A  INFO   MTP: link bypassed SLT phase

Alarm Level: No alarm condition. The message is informational only.

Recovery

  1. Enter the rtrv-slk command with the card location and port shown in this message (for example, card location 1201, port A).
    Example of the output:
    tekelecstp 00-02-19 21:17:04 EST EAGLE 35.0.0
    rtrv-slk:loc = 1202:port = a
    Command entered at terminal #3. 
    tekelecstp 94-02-19 21:17:04 EST EAGLE 35.0.0
                                           L2T         L1               PCR  PCR
    LOC  PORT LSN         SLC TYPE     SET  BPS    MODE TSET  ECM   N1   N2
    1201 A    lsa1         0  LIMV35   2    64000  DTE  ---   PCR   ---  3800
  2. Use the rtrv-ls command using the linkset name (lsn) displayed in the output of 1 .
    Example of the output:
    >  rtrv-ls:lsn = lsa1
    tekelecstp 00-06-10 11:43:04 EST EAGLE 35.0.0
                               SCR   L3T  SLT
        LSN       APCA (SS7)   SET   SET  SET BEI  LST LNKS GWSA GWSM GWSD DOMAIN
        lsa1      240-020-000  scr1  1    1   yes  A   4    off  off  off  SS7
                  TFATCABMLQ
                  2
                                          L2T          L1              PCR  PCR 
                  LOC   PORT SLC TYPE     SET  BPS    MODE TSET  ECM   N1   N2
                  1201  a    3   LIMV35   2    64000  DTE  ---   BASIC ---  -----
                  1205  b    0   LIMDS0   1    56000  ---  ---   BASIC ---  -----
                    b    1   LIMOCU   1    56000  ---  ---   BASIC ---  -----
                  1211  a    2   LIMDS0   1    56000  ---  ---   BASIC ---  -----
        Link set table is (114 of 255) 45% full.
  3. Enter the rtrv-slt command with the sltset parameter and the value shown in the SLTSET column from the output of Step 2 to determine whether the signaling link test message is on or off.
  4. If the signaling link test message is off, enter the chg-slt command with the sltset parameter and the value used in Step 3, and the enabled=on parameter.
  5. If the signaling link test message is on, enter the rept-stat-card command to verify the status of the card that contains the specified signaling link.
    The status of the card should be IS-NR (In-Service - Normal).
  6. If the card is out of service, put it back into service by entering the rst-card command.
  7. If the fault is not cleared, enter the rept-stat-slk command to verify the status of the signaling link.
    The status of the signaling should be IS-NR (In-Service - Normal).
  8. If the signaling link is out of service, enter the act-slk command to put the signaling link back into service.
  9. If the fault is not cleared, enter the tst-slk command specifying the signaling link that generated this message.
  10. If the fault is not cleared, contact My Oracle Support (MOS).