Contract Administration for Head Contractors
Once a project is set up on the system, subcontracts can be created. Subcontracts can be created manually or imported.
Manually Create Subcontracts
- Use the Add button on the Subcontract List page, or select Create Subcontract from the Subcontracts drop-down menu to create a subcontract.
- Manually enter Subcontractor information and contract settings
- Add components to create separate cost items within the contract, then enter the value of each component and be sure to add a task code if GST should apply.
See Tax Codes.
Note: If you use an accounting interface with the system, you should not manually create subcontracts.
Import Subcontracts
Subcontracts entered in an accounting package can be imported into the system using the accounting interface.