View/Edit Potential Variations

As a Subcontractor, use the the View / Edit Potential Variations link on the Period Home page or during claim submission to request a variation.

Note: if you do not have a View / Edit Potential Variations option, the Head Contractor is likely using a different variation system.

See Request Variations Tab.

Select the Add New Row button to create a row in which you will enter the variation. Fill in all Subcontractor Data fields:

Select Save Changes to save your variations. All potential variations in the current claim period will be included on your progress claim as Potential Variations.

Deleting Potential Variations

You can only delete variations in the period in which they are submitted prior to claim submission. Select the red X at the end of each line to mark lines for deletion. Lines pending deletion will be highlighted in grey and are removed upon saving changes.

Variation Status

Variation Status can be changed by either the Subcontractor or the Head Contractor. Variations with a Closed status will remain on the View/Edit Potential Variations screen for reference, but will not show on claim documents.

Head Contractor Data

The Head Contractor Data is entered by the Head Contractor as part of assessing potential variations:

Filtering Potential Variations

Potential Variations can be filtered using the radio buttons above the table:

Find the Edit Potential Variations Screen

Based on project settings, the system generates the View/Edit Potential Variations action once your Billing Workflow is completed.
See Submitting a Progress Claim for Subcontractors.