Head Contractor Status Message
The Status page confirms you successfully completed actions in the application and can include Next Steps or Additional Pending Project Actions.
- Bold Message: Confirms you completed your last action.
- Next Steps: Contains links to additional actions required to complete the current workflow. For example:- When setting up an account, after creating a username and password, the next action will be to update the User Profile.
 See Edit User for Head Contractors.
- When submitting a client billing progress claim, after entering claim values, the next action will be to generate progress claim documents.
 See Reviewing your Billing and Proceeding to Signing.
 
- When setting up an account, after creating a username and password, the next action will be to update the User Profile.
- (Optional) Additional Pending Actions: Only appears when there are additional actions to complete from a different workflow. Actions can include:- Assessing submitted progress claims
 See Manage Claims.
- Reviewing submitted compliance documents
 See Head Contractor Compliance Overview.
- Modifying the Work Breakdown.
 See About Modifying the Work Breakdown.
 
- Assessing submitted progress claims