Contract Status Fields

Summary Section

Organisation

Displays the Subcontractor's name and acts as an organisation lookup. To look up an organisation, enter its name to look up contracts with that organisation. You can also use this field to select another Subcontractor. When entering an organisation's name, the auto-complete will list matching on-system organisations. Selecting an organisation will populate the project drop-down.

Project

This drop-down field displays the project name. You can use this field to select another contract with this Subcontractor. Below the project, a message will display the period context.

Period Context

Below the project, a message displays the period context.

Location

The location and phone number of the Subcontractor.

Contract

The contract number and description of the contract.

Vendor ID

An accounting package identifier for the Subcontractor.

Contract Comment

An optional comment included as a message on the contract. This is a view only field, you can edit this comment on either the Contract Maintenance, Edit Payment Status, or Owner Funding Entry page.

Discount Terms

Cash discount settings include the discount rate (%), number of days the subcontract must meet to trigger the discount, and the trigger date.

Summary Amounts

Contract Amount

Original: The amount of the original contract.

Varitations: Variations that alter contract amount.

Adjusted: The contract amount including variation adjustments.

Unapproved Variations: The value of variations requested by the subcontractor but not yet approved in an accounting package.

Potential Contract Value: The value of the subcontract if all unapproved variations became approved. Unapproved Variations and Potential Contract Value will only be displayed on projects using the Variation Register.

See Variation Register Tab.

Approved Progress Claims

Gross: The total amount for approved progress claims.

Retention Held: The amount held from the approved progress claims.

Net: The amount for approved progress claims after the retention is held.

Payments

Latest Date: Last date the Subcontractor was paid.

Current Payable: The amount currently due to the Subcontractor.

Total Payments: The total amount paid to the Subcontractor, including current payments.

Items not Exported

Approved Progress Claims: Total value of progress claims.

Payments: Total amount paid.

Pending and Paid Periods

Period

Pending Period: Lists the pending period; Choose the period number to see the Period Home page.

Paid Period: Lists the most recent period.

Period To Date

The end date for the period.

Method

The payment method (EFT, Manual Cheque, etc.).

% Complete

Displays the % complete against the selected draw.

Gross Pr. Claim

The total amount the Subcontractor billed, or has been approved.

Retention

Retention held against the claim.

Net Pr. Claim

The total claim minus the retention.

Discount

The discount amount for each claim. This column is displayed only when fixed or variable discounts are enabled on the contract.

Tax

Tax applied to the progress claim

Payment

Pending Pmt: Entire payment for the pending period.

Payments: Entire payment for the paid period.

Total Pending: Amount of payment pending.

Payment Due Date: Date payment is due based on the Project Settings page.

See Choose Project Settings.

The Payment Due Date field will remain empty unless a project and contract has a payment due date set up.

See Calculating Payment Due Dates.

Date Paid

Date payment was sent to the Subcontractor.

Paid To Date

Amount of payment already made for the period.

Status

Payment status; choose the Manage Payment link to the Edit Payment Status page.

See Edit Payment Status.

Comments

Any comments included in the payment.

Documents

Documents included in the period are listed:

Progress Claim

Payment Schedule

Statutory Declaration

Attachments

See Attachments Page for Head Contractors.

Expanded View

If the Expanded View option is selected, the Period section will include:

Claim Date

The date the progress claim was submitted.

Pr. Claim Number

The reference number for the progress claim.

Cheque

The cheque number (for manual payments).

Date Paid

The date the Subcontractor was paid.

Pr. Claim Export

Date the approved claim was exported to the accounting system.

Payment Export

Date the payment was exported to the accounting system.

Contracts with Textura Payment Accelerator programs

The Contract Status page shows TPA in the Method column. It also includes a Funded column and reflects that a Subcontractor participates in the TPA.

Method

Displays TPA.

Funded

Shows the amount paid to the Subcontractor once the approved claim is funded.

Funded Date (part of the expanded view)

Displays the effective date of funding (the date the Subcontractor was paid).

Status

The Status column will include more statuses for TPA projects.

 

Before Disbursement

After Disbursement

After a Progress Claim is Funded

After Maturity

Status

Awaiting, Received, or Approved

Funding

Funded

Paid

See Manage Textura Payment Accelerator programs for Head Contractors or Contact your implementation team to learn more about Textura Payment Accelerator programs.

Variations Table

Approved Variations

Variations

Reference number for the variation.

Date Entered

Date the variation was added to the project.

Var Date

Date for accounting purposes.

Period

Period the variation affects.

Title

Name of the variation.

Description

Variation description.

Amount

Amount the contract is adjusted by.

Total Vars to Date

The amount of all approved variations to date.

Adj. Contract

The Contract total including variations

Requested Variations

The Requested Variations section will only be displayed if there are unapproved variations on projects using the Variation Register.

See Variation Register Tab.

Requested Variations

Reference number for the variation.

Submitted Date

Date the Subcontractor submitted the variation request.

Period

The claims period in which the subcontractor submitted the request.

Title

Name of the variation.

Description

Variation description.

Submitted Amount

Value of the variation as requested by the Subcontractor.

Submitted to Date

The total value of submitted variations.

Billed to Date

Total value of claims against submitted variations.

Actions and Contacts

Pending Actions

Pending Actions

Date the action was generated.

Description

Action required to be completed.

Organisation

Which organisation (usually the Head Contractor or the Subcontractor) is required to complete the action.

User Role(s)

Which users are able to complete the action.

Contacts

Contacts

User's name.

Title

User's company title.

Roles

User's role on the system.

Email

User's email address for the system.

Phone/Fax/Mobile

User's contact numbers.