Edit WB Tab Overview
The Edit WB tab is the project budget or Work Breakdown. Use this tab to view the budget and adjust un-billed line items.
Adjustment Amount
Column used to change line item amounts.
Work Breakdown Value Amount
Current value for the line item. This includes the Adjustment Amount.
Net Change by Variation Amount
Total value of variations (positive or negative) that impacts the line item.
Contract Sum to Date Amount
Value of the line item plus the Net Change by Variation amount.
Billed To Date Amount
Amount invoiced to date. This value changes based on period context.
% Comp
Percentage of the line item completed so far.
Retention to Date Amount
Amount of retention held back.
Balance to Complete
Amount left to bill on the contract (the total amount of work outstanding on the contract). This amount is equal to the Contract Sum to Date Amount minus the Billed to Date Amount.