Recording Progress Billing for Subcontractors

To enter progress billing details as a Subcontractor on the Progress tab of your Billing Workflow:

  1. Navigate to your Billing Workflow for Subcontractors
    • The Progress tab will display first for most users beginning the claiming process.
    • If a project allows stored material tracking, this will be the second tab in the claiming process.
    • If the current period does not allow progress billing, you will not see this tab.
  2. Enter billing amounts:
    1. Choose a line to bill against. The selected field will have a darker border than the other cells in the table.

      Unable to edit a field? Some Head Contractors use component types to specify how labour or stored materials can be billed. Subcontractor billing is then limited by the component type.

    2. Enter an amount under the Work This Period column. 

      Once an amount billed is entered:

      • Amounts in the % CompleteCompleted to Date, and Net This Period are automatically calculated
      • The Retention Held This Period amount is automatically calculated.
        The retention calculation is based on the project's default percentage.
  3. Optional. Add comments to a line for later review or as a message to an on-system user. The line item comments entered here are visible to your Head Contractor when they view or modify your progress claim.
    1. In the Description of Work column, select the speech button icon.

      A Comments and History dialogue box displays.

    2. In the available field in the dialogue box, enter your comment.
    3. Select Ok.

      The dialogue box closes and the speech bubble icon turns blue. Select the blue icon to view available comments.

  4. Check the claim totals at the bottom of the page.
  5. Select the Save & Continue button to progress to the next tab in your Billing Workflow.

There are two additional ways to update billing totals on the Progress tab:

  1. Bill for a completed percentage
  2. Bill for stored materials.

Bill % Complete

To bill based on percentage, update the amount in the % Complete fieldThe Work This Period field shows the dollar amount. All other fields are automatically calculated.

Tip

Claim amounts may not exceed the remaining balance for any line item.

Bill for Material Stored This Period

Enter the dollar amount of material stored between the Period From and Period To dates in the Material Stored This Period field.

Notes: