View Draw Request

The View Draw Request SoV and SC pages show draw history/invoice information in table form. Each provides a snapshot of draw data for reference purposes.

View Draw Request – SoV

See a line-by-line breakdown of approved Subcontractor invoices and self-performed amounts on the View Draw Request – SoV tab.

View Draw Request – SC

See a summary of all data, including the selected draw (the draw identified at the top of the page) on the View Draw Request – SC tab. Use this tab to quickly verify amounts billed for each Subcontract, the percentage of work completed, retention held, and whether or not change orders are included in that period data. Document links appear based on the Document Settings selected by the General Contractor on the Project Settings page.

Note: The SoV is short for Schedule of Values and SC is short for Subcontract.