Draw Request Fields
The following columns are displayed on both pages (View Draw Request - SoV and View Draw Request - SC):
Description
Describes the line item.
Scheduled Values
Current value for the line item–includes Adjustment Amount.
Work Completed
From Previous Application—Dollar amount of the work completed through the last draw period.
This Period—Dollar amount of the work completed between the draw Period From and Period To dates.
Material Stored This Period
Dollar amount of material stored between the draw Period From and Period To dates.
Total Completed and Stored to Date
Dollar amount of the material completed and stored from the start of the project (Work Completed From Previous Application + Work Completed This Period + Material Stored This Period).
% Complete
The percentage of work completed in the current draw and all previous draws.
Balance Due
The amount left on the contract.
Retention
This Period—The dollar amount for the work completed between the draw Period From and Period To dates.
Balance—The total amount of retention being held for the line.
View Draw Request – SoV
It includes an additional column:
Phase Code
The number used to sort line items sequentially.
View Draw Request – SC
The table is organized by subcontract. It includes the following additional columns:
Sub Contract Number
Links to the View Draw Request-SoV page for the subcontract.
Sub Contractor Description
Identifies the Subcontractor.