Changing a Discount During Discount Terms
You can modify the discount amount up until the date the discount applies.
Note: This option modifies the discount on a single payment. You can use this feature on contracts with either rate type (variable or fixed rate discounts).
To update a discount inside of the established discount terms:
- Navigate to the Payment Status Page
To access the Payment Status page:
- From the Payment/Lien Waivers section of the Draw Home page, select the Manage Payments link.
- From the Edit column on the Manage Draw Payments page, select the Edit link.
- From the Discount Tile, select Edit.
Discount fields display.
Note: The Discount Tile, displays as Change CCIP Discount if your project uses CCIP for variable discount.
- Either:
- Change the discount percentage: Select the Percentage option and enter a new numeric value.
Note: When you select the Percent Discount field, the application will mention the maximum discount value you can apply.
- Change the discount amount: Select the Amount option and enter a new monetary value.
- Change the discount percentage: Select the Percentage option and enter a new numeric value.
- Select Update.
- A Discount updated successfully message displays at the bottom of the page.
- The additional editable fields collapse and the Discount Tile displays both the new discount total in the project's currency and the date you changed the discount.