Changing a Discount During Discount Terms

You can modify the discount amount up until the date the discount applies.

Note: This option modifies the discount on a single payment. You can use this feature on contracts with either rate type (variable or fixed rate discounts).

To update a discount inside of the established discount terms:

  1. Navigate to the Payment Status Page
  2. From the Discount Tile, select Edit.

    Discount fields display.

    Note: The Discount Tile, displays as Change CCIP Discount if your project uses CCIP for variable discount.

  3. Either:
    • Change the discount percentage: Select the Percentage option and enter a new numeric value.

      Note: When you select the Percent Discount field, the application will mention the maximum discount value you can apply.

    • Change the discount amount: Select the Amount option and enter a new monetary value.
  4. Select Update.
    • A Discount updated successfully message displays at the bottom of the page.
    • The additional editable fields collapse and the Discount Tile displays both the new discount total in the project's currency and the date you changed the discount.