Changing a Discount After Discount Terms Pass

If the discount date/terms have passed, you can request a Subcontractor accept the discount outside of terms.

Note: If needed, you can withdraw the discount outside of terms while awaiting Subcontractor approval and send a revised discount.

  1. Navigate to the Payment Status Page
  2. From the Discount Tile, select Edit.

    Discount fields display.

    Note: The Discount Tile, displays as Change CCIP Discount if your project uses CCIP for variable discount.

  3. Either:
    • Change the discount percentage: Select the Percentage option and enter a new numeric value.

      Note: When you select the Percent Discount field, the application will mention the maximum discount value you can apply.

    • Change the discount amount: Select the Amount option and enter a new monetary value.
  4. Select Submit for Approval.

    Note: A Subcontractor must accept the discount outside of terms to remove the automatic hold placed upon payments.