Changing a Discount After Discount Terms Pass

If the discount date/terms have passed, you can request a Subcontractor accept the discount outside of terms.

  1. Navigate to the Edit Payment Status Page
  2. Enter the discount amount in the Change Discount field.

    Note: The field Change Discount, is displayed as Change CCIP Discount if your project uses CCIP for variable discount.

  3. Choose Submit for Approval.

    Note: A Subcontractor must accept the discount outside of terms to remove the automatic hold placed upon payments.